City of Walla Walla Mill Creek Hydroelectric

City of Walla Walla Mill Creek Hydroelectric is a 3.0 MW hydro request built and operating in the West interconnection queue, in Walla Walla County, Washington, connecting to Columbia Rural Electric Association.

Queue statusOperating
  1. PlanningQueued Jun 2012 (completed)
  2. ConsentedDec 2012 (completed)
  3. Construction (completed)
  4. OperatingTarget Jan 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G0475
Grid region
West (non-ISO utilities)
Utility / transmission owner
Columbia Rural Electric Association
Connection point (POI)
Walla Walla Substation point of delivery #4048.
Location
Walla Walla County, Washington
Technology
Hydro: 3.0 MW
Total requested
3.0 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
21 June 2012
Agreement signed
17 December 2012
Proposed online date
January 2013

Location

Marker shows the centre of Walla Walla County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Walla Walla County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem