🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Washington

ONSHORE WIND · WEST

Onshore wind project T2-022, Walla Walla County

Onshore wind project T2-022, Walla Walla County is a 100 MW onshore wind request in interconnection study in the West interconnection queue, in Walla Walla County, Washington, connecting to PacifiCorp.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
T2-022
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Wallula substation
Location
Walla Walla County, Washington
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Queue status
Active
Entered queue
4 September 2025
Proposed online date
December 2026

Location

Marker shows the centre of Walla Walla County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Walla Walla County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem