🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Utah

SOLAR · WEST

Solar project 489, Iron County

Solar project 489, Iron County is a 3.0 MW solar request built and operating in the West interconnection queue, in Iron County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Mar 2013 (completed)
  2. ConsentedMar 2014 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
489
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Cedar Valley Solar, LLC
Connection point (POI)
Circuit ENO12, Enoch#12, out of Enoch substation
Location
Iron County, Utah
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Network resource (NRIS)
Study phase
IA signed March 27, 2014
Queue status
Operational
Entered queue
19 March 2013
Agreement signed
27 March 2014
Proposed online date
December 2015

Location

Marker shows the centre of Iron County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Iron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem