🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Arizona

SOLAR · WEST

Solar project Q213, Yuma County

Solar project Q213, Yuma County is a 3.0 MW solar request built and operating in the West interconnection queue, in Yuma County, Arizona, connecting to Arizona Public Service.

Queue statusOperating
  1. PlanningQueued May 2012 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q213
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Desert Sands 69kv switchyard
Location
Yuma County, Arizona
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Network resource (NRIS)
Study phase
In-Service
Queue status
Operational
Entered queue
15 May 2012
Proposed online date
December 2012

Location

Marker shows the centre of Yuma County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Yuma County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem