Withdrawn queue requests in the USA — page 83

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 83 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2008-076, Barber County
Onshore wind
300 MWWithdrawn / abandoned Barber, KSSPP Jul 2008target 2011
Solar + storage project 764, Minidoka County
Solar + storage
300 MWWithdrawn / abandoned Minidoka, IDWest Mar 2025
Onshore wind project GEN-2014-058, Blaine County
Onshore wind
300 MWWithdrawn / abandoned Blaine, OKSPP Sep 2014target 2016
Top Crop Wind Farm
Onshore wind
300 MWWithdrawn / abandoned Livingston, ILPJM May 2005target 2013
MykawaAlta
Gas · Alta Power LLC
300 MWWithdrawn / abandoned Harris, TXERCOT Aug 2019target 2021
Solar project J3562, Vermilion County
Solar
300 MWWithdrawn / abandoned Vermilion, ILMISO Apr 2024target 2028
Onshore wind project GEN-2008-020, Dewey County
Onshore wind
300 MWWithdrawn / abandoned Dewey, OKSPP Mar 2008target 2012
Solar project J3499, Kosciusko County
Solar
300 MWWithdrawn / abandoned Kosciusko, INMISO Apr 2024target 2028
Solar + storage project Q385, Pinal County
Solar + storage
300 MWWithdrawn / abandoned Pinal, AZWest Mar 2021target 2025
Swift Solar
Solar + storage · Swift Solar LLC
300 MWWithdrawn / abandoned Herkimer, NYNYISO Jun 2022
Onshore wind project J1676, Mclean County
Onshore wind
300 MWWithdrawn / abandoned Mclean, ILMISO Jun 2020target 2023
Solar project Q32, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Aug 2007target 2010
Other project IA-PNM-2014-01, Guadalupe Cty County
Other
300 MWWithdrawn / abandoned Guadalupe Cty, NMWest Feb 2014target 2015
Battery storage project J2419, Faribault County
Battery storage
300 MWWithdrawn / abandoned Faribault, MNMISO Sep 2022target 2027
Arco Solar Station
Solar
300 MWWithdrawn / abandoned Kern, CACAISO Jul 2010target 2014
Onshore wind project G0296, Morrow County
Onshore wind
300 MWWithdrawn / abandoned Morrow, ORWest Oct 2007target 2012
Gas project J130, Hancock County
Gas
300 MWWithdrawn / abandoned Hancock, IAMISO Apr 2010target 2011
Cathode
Battery storage
300 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2024
Other project G116, Knox County
Other
300 MWWithdrawn / abandoned Knox, INMISO Aug 2001target 2005
Solar project 1049, Utah County
Solar
300 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Solar + storage project 1220, Klamath County
Solar + storage
300 MWWithdrawn / abandoned Klamath, ORWest Apr 2020target 2023
Solar project J3569, Poinsett County
Solar
300 MWWithdrawn / abandoned Poinsett, ARMISO Apr 2024target 2028
Onshore wind project W3-014, Crawford County
Onshore wind
300 MWWithdrawn / abandoned Crawford, OHPJM Aug 2010target 2013
Solar project GI-2021-21, Pueblo County
Solar
300 MWWithdrawn / abandoned Pueblo, COWest Oct 2021target 2024
Solar + storage project GEN-2021-075, Camp County
Solar + storage
300 MWWithdrawn / abandoned Camp, TXSPP May 2021target 2027
Nacogdoches CC Generating Facility
Gas · Nacogdoches Power, LLC
300 MWWithdrawn / abandoned ERCOT Dec 2006
GYPSY ESS 2
Battery storage
300 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2024
Solar + storage project Company KE, Churchill County
Solar + storage
300 MWWithdrawn / abandoned Churchill, NVWest Sep 2019target 2022
Solar + storage project Q15, Pinal County
Solar + storage
300 MWWithdrawn / abandoned Pinal, AZWest Sep 2020target 2023
Gas project B07, Armstrong County
Gas
300 MWWithdrawn / abandoned Armstrong, PAPJM May 1999
Battery storage project GEN-2024-SR4, Yoakum County
Battery storage
300 MWWithdrawn / abandoned Yoakum, TXSPP Dec 2023target 2026
Solar + storage project GEN-2023-086, Randall County
Solar + storage
300 MWWithdrawn / abandoned Randall, TXSPP Oct 2023target 2029
Battery storage project J2504, Coles County
Battery storage
300 MWWithdrawn / abandoned Coles, ILMISO Sep 2022target 2026
HI300SB Project
Solar + storage
300 MWWithdrawn / abandoned Grant, NMWest Mar 2020target 2022
Battery Storage
Battery storage
300 MWWithdrawn / abandoned Hampden, MAISO-NE Nov 2022target 2025
Onshore wind project GEN-2015-068, Hale County
Onshore wind
300 MWWithdrawn / abandoned Hale, TXSPP Oct 2015target 2017
Solar project 1050, Utah County
Solar
300 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Solar project GEN-2024-349, Hall County
Solar
300 MWWithdrawn / abandoned Hall, NESPP Mar 2025target 2029
Solar project GEN-2017-209, Mcpherson County
Solar
300 MWWithdrawn / abandoned Mcpherson, KSSPP Nov 2017target 2026
Battery storage project GEN-2022-132, Caddo County
Battery storage
300 MWWithdrawn / abandoned Caddo, OKSPP Feb 2023target 2027
Windwood Wind
Onshore wind · Lincoln Clean
300 MWWithdrawn / abandoned ERCOT Jun 2012target 2018
Onshore wind project GI-2008-2, Huerfano County
Onshore wind
300 MWWithdrawn / abandoned Huerfano, COWest Mar 2008target 2009
Gas project 498, Sweetwater County
Gas
300 MWWithdrawn / abandoned Sweetwater, WYWest Jun 2013target 2016
Onshore wind project J2327, Lamoure County
Onshore wind
300 MWWithdrawn / abandoned Lamoure, NDMISO Sep 2022target 2026
Russell Station II
Coal · RG&E
300 MWWithdrawn / abandoned Monroe, NYNYISO Jun 2007
Solar + storage project J3088, Woodbury County
Solar + storage
300 MWWithdrawn / abandoned Woodbury, IAMISO Sep 2022target 2027
Onshore wind project J1702, Shelby County
Onshore wind
300 MWWithdrawn / abandoned Shelby, ILMISO Jun 2020target 2023
Onshore wind project J3700, Champaign County
Onshore wind
300 MWWithdrawn / abandoned Champaign, ILMISO Apr 2024target 2028
Onshore wind project GI-2003-1, Morgan County
Onshore wind
300 MWWithdrawn / abandoned Morgan, COWest Oct 2003target 2006
Solar project J2090, Crittenden County
Solar
300 MWWithdrawn / abandoned Crittenden, ARMISO Jul 2022target 2026
Page 83 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)