United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

BATTERY STORAGE Β· SPP

Battery storage project GEN-2022-132, Caddo County

Battery storage project GEN-2022-132, Caddo County is a 300 MW battery storage request withdrawn in the SPP interconnection queue, in Caddo County, Oklahoma, connecting to WFEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-132
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WFEC
Connection point (POI)
Anadarko 138kV Substation
Location
Caddo County, Oklahoma
Technology
Battery: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
21 February 2023
Proposed online date
December 2027
Withdrawn
March 2025

Location

Marker shows the centre of Caddo County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Caddo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem