Requests shown4,787563.7 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4,787 requests · page 83 of 96
ProjectCapacityStatusLocationRegionQueuedOnline
Westminster - NG Western MA Area Cluster Study
Solar
4.9 MWOperating Worcester, MAISO-NE Dec 2018target 2021
Gas project ASGI-2016-013
Gas
4.9 MWOperating SPP
Other project 360, Morrow County
Other · TMF Biofuels, LLC
4.8 MWOperating Morrow, ORWest Nov 2010target 2013
Hydro project 687, Lincoln County
Hydro · American Falls Reservoir District No. 2
4.8 MWOperating Lincoln, IDWest Nov 2022target 2023
Other project 129, Salt Lake County
Other · Energy Developments South Jordan, LLC
4.8 MWOperating Salt Lake, UTWest Mar 2007target 2009
Solar project 577, Klamath County
Solar · NorWest Energy 4, LLC
4.8 MWOperating Klamath, ORWest May 2014target 2018
Bio Energy Landfill Facility
Other
4.8 MWOperating Brown, OHPJM Apr 20152017
Chrin LF
Other
4.8 MWOperating Northampton, PAPJM Sep 20092011
Gas project GEN-2012-021, Lancaster County
Gas
4.8 MWOperating Lancaster, NESPP Sep 20122013
Solar
Solar
4.8 MWOperating York, MEISO-NE Aug 2019target 2022
ENA Old Falmouth Road PV + Storage
Solar + storage
4.8 MWOperating Barnstable, MAISO-NE Apr 2020target 2024
Shoreham Energy Units 1-3
Other
4.8 MWOperating Atlantic, NJPJM Jan 20072008
Cumberland County Landfill
Other
4.8 MWOperating Cumberland, PAPJM May 20102012
Moretown Landfill
Other
4.8 MWOperating Washington, VTISO-NE Nov 2007target 2008
Gas project 702, Canyon County
Gas · City of Nampa‚ÄîWastewater Division
4.8 MWOperating Canyon, IDWest Feb 20232023
Wabash Valley Power Association, Inc.
Other
4.8 MWOperating Elkhart, INPJM Jan 20132015
Merrimack Unit 2 Uprate
Coal
4.7 MWOperating Merrimack, NHISO-NE Apr 2008target 2008
Moore Station Uprate
Hydro
4.6 MWOperating Grafton, NHISO-NE Apr 2016target 2023
Solar
Solar
4.6 MWOperating Oxford, MEISO-NE Aug 2019target 2021
Hydro project GEN-2010-036, Douglas County
Hydro
4.6 MWOperating Douglas, KSSPP Jun 20102012
Watervliet Solar Facility
Solar
4.6 MWOperating Berrien, MIPJM Apr 20142016
Solar
Solar
4.6 MWOperating Oxford, MEISO-NE Aug 2019target 2021
Other project hist_q15, Jerome County
Other
4.5 MWOperating Jerome, IDWest
Solar project 425, Malheur County
Solar
4.5 MWOperating Malheur, ORWest Jan 2014target 2016
Other project 348, Lincoln County
Other
4.5 MWOperating Lincoln, IDWest Aug 20102011
Onshore wind project GEN-2015-062, Garfield County
Onshore wind
4.5 MWOperating Garfield, OKSPP Oct 20152024
Grand Ridge Battery Storage
Battery storage
4.5 MWOperating Lasalle, ILPJM Jul 20122012
White Oak
Gas
4.5 MWOperating Montgomery, MDPJM Jul 20092010
Gas project GEN-2010-055, Tulsa County
Gas
4.5 MWOperating Tulsa, OKSPP Sep 20102013
Otter Point LF-1
Other
4.5 MWOperating Baltimore, MDPJM Jun 20042006
Hydro project GEN-2011-056B, Dawson County
Hydro
4.5 MWOperating Dawson, NESPP Mar 20122012
Gulf Island Unit 2 Increase
Hydro
4.4 MWOperating Androscoggin, MEISO-NE Dec 2010target 2011
Augusta E. Side 115 kV SS - Augusta Area Study
Solar + storage
4.3 MWOperating Kennebec, MEISO-NE Oct 2020target 2022
Hydro project 1012, Jefferson County
Hydro · Deschutes Valley Water District
4.3 MWOperating Jefferson, ORWest Mar 2018target 2020
Pinesburg Solar Project
Solar
4.3 MWOperating Washington, MDPJM Oct 20142020
Ridgewood RI Generation Phase I
Other
4.2 MWOperating Providence, RIISO-NE Mar 2003target 2004
Hydro project 1055, Shasta County
Hydro · Slate Creek Hydro Associates LP
4.2 MWOperating Shasta, CAWest Jul 2018target 2020
Upton
Other
4.1 MWOperating Franklin, PAPJM Jul 20022004
Morris Road
Other
4.1 MWOperating Montgomery, PAPJM Aug 20152020
Other project BADM, Ada County
Other
4.1 MWOperating Ada, IDWest
Augusta E. Side 115 kV SS - Augusta Area Study
Solar
4.0 MWOperating Kennebec, MEISO-NE Oct 2020target 2022
Holmdel SP
Solar
4.0 MWOperating Monmouth, NJPJM Apr 20102013
Vineland-Mays Landing
Solar
4.0 MWOperating Cumberland, NJPJM Jul 20092011
Buck & Byllesby Hydro Project
Battery storage
4.0 MWOperating Carroll, VAPJM Apr 20182019
Combined Cycle Upgrade
Gas
4.0 MWOperating Fairfield, CTISO-NE Mar 2020target 2021
Onshore wind project GEN-2014-004, Jefferson County
Onshore wind
4.0 MWOperating Jefferson, NESPP Feb 20142013
Other project J406, Wexford County
Other
4.0 MWOperating Wexford, MIMISO Nov 20142018
Eastern Landfill Gas
Other
4.0 MWOperating Baltimore, MDPJM Oct 20122016
Onshore wind project G185, Pipestone County
Onshore wind
4.0 MWOperating Pipestone, MNMISO Mar 20022004
Ameresco Butte County Landfill
Other
4.0 MWOperating Butte, CACAISO Feb 20092012
Page 83 of 96

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)