BATTERY STORAGE · PJMBuck & Byllesby Hydro Project
Buck & Byllesby Hydro Project is a 4.0 MW battery storage request built and operating in the PJM interconnection queue, in Carroll County, Virginia, connecting to AEP.
Request details
- Queue ID
- AD2-205
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Byllesby 69 kV
- Location
- Carroll County, Virginia
- Technology
- Battery: 4.0 MW
- Total requested
- 4.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 13 April 2018
- Proposed online date
- December 2018
- Came online
- January 2019
Location
Marker shows the centre of Carroll County; the queue data does not give exact sites.
Other requests in Carroll County
- Solar + storage project AH1-098, Carroll CountySolar + storage · 40.0 MW · in study
- Solar project AG2-190, Carroll CountySolar · 77.4 MW · withdrawn
- Solar + storage project AG2-603, Carroll CountySolar + storage · 77.0 MW · withdrawn
- Poplar CampOnshore wind · 72.0 MW · withdrawn
- Solar project AH1-172, Carroll CountySolar · 20.0 MW · withdrawn
- Solar + storage project AH1-097, Carroll CountySolar + storage · 20.0 MW · withdrawn
- Solar project AH1-177, Carroll CountySolar · 10.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem