Grand Ridge Battery Storage

Grand Ridge Battery Storage is a 4.5 MW battery storage request built and operating in the PJM interconnection queue, in Lasalle County, Illinois, connecting to ComEd.

Queue statusOperating
  1. PlanningQueued Jul 2012 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y2-043
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Kickapoo
Location
Lasalle County, Illinois
Technology
Battery: 4.5 MW
Total requested
4.5 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
30 July 2012
Proposed online date
December 2012
Came online
December 2012

Location

Marker shows the centre of Lasalle County; the queue data does not give exact sites.