United States › Grid › Interconnection queues › New Hampshire
COAL · ISO-NEMerrimack Unit 2 Uprate
Merrimack Unit 2 Uprate is a 4.7 MW coal request built and operating in the ISO-NE interconnection queue, in Merrimack County, New Hampshire.
Request details
- Queue ID
- 258
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- PSNH Merrimack Substation
- Location
- Merrimack County, New Hampshire
- Technology
- Coal: 4.7 MW
- Total requested
- 4.7 MW
- Service type
- Other
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 15 April 2008
- Proposed online date
- May 2008
Location
Marker shows the centre of Merrimack County; the queue data does not give exact sites.
Power plants in New Hampshire · Transmission lines in New Hampshire
Other requests in Merrimack County
- Merrimack Unit 2 Second UprateCoal · 17.2 MW · built
- Battery StorageBattery storage · 226 MW · withdrawn
- WindOnshore wind · 80.0 MW · withdrawn
- SolarSolar · 76.3 MW · withdrawn
- WindOnshore wind · 74.3 MW · withdrawn
- Solar plus BatterySolar + storage · 53.1 MW · withdrawn
- SolarSolar · 35.0 MW · withdrawn
- Battery StorageBattery storage · 20.0 MW · withdrawn
- Steam TurbineOther · 20.0 MW · withdrawn
- Pembroke SolarSolar · 17.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem