πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Hampshire

OTHER Β· ISO-NE

Steam Turbine

Steam Turbine is a 20.0 MW other request withdrawn in the ISO-NE interconnection queue, in Merrimack County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2008 (completed)
  2. Withdrawn / abandonedMar 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
256
Grid region
ISO-NE (New England)
Connection point (POI)
Unitil 34.5kV line from PSNH Garvins station to UE
Location
Merrimack County, New Hampshire
Technology
Other: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
4 April 2008
Proposed online date
March 2013
Withdrawn
March 2013

Location

Marker shows the centre of Merrimack County; the queue data does not give exact sites.

Power plants in New Hampshire Β· Transmission lines in New Hampshire

Other requests in Merrimack County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem