COAL · ISO-NE

Merrimack Unit 2 Second Uprate

Merrimack Unit 2 Second Uprate is a 17.2 MW coal request built and operating in the ISO-NE interconnection queue, in Merrimack County, New Hampshire.

Queue statusOperating
  1. PlanningQueued Jan 2009 (completed)
  2. ConsentedOct 2019 (completed)
  3. Construction (completed)
  4. OperatingTarget Jun 2010 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
291
Grid region
ISO-NE (New England)
Connection point (POI)
PSNH Merrimack Substation
Location
Merrimack County, New Hampshire
Technology
Coal: 17.2 MW
Total requested
17.2 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
21 January 2009
Agreement signed
8 October 2019
Proposed online date
June 2010

Location

Marker shows the centre of Merrimack County; the queue data does not give exact sites.