United States › Grid › Interconnection queues › Vermont
OTHER · ISO-NEMoretown Landfill
Moretown Landfill is a 4.8 MW other request built and operating in the ISO-NE interconnection queue, in Washington County, Vermont.
Request details
- Queue ID
- 234
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Green Mountain Power 34 kV feeder
- Location
- Washington County, Vermont
- Technology
- Other: 4.8 MW
- Total requested
- 4.8 MW
- Service type
- Other
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 7 November 2007
- Proposed online date
- September 2008