United States › Grid › Interconnection queues › Washington

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Washington — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown499103.5 GW
Active in queue58.5 GW207 requests
Agreement signed3,095 MW26 requests
Withdrawn499103.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

499 requests · page 8 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project C2-35, Yakima County
Solar + storage
80.0 MWWithdrawn / abandoned Yakima, WAWest Apr 2022target 2025
Solar project G0564, Franklin County
Solar
80.0 MWWithdrawn / abandoned Franklin, WAWest May 2017target 2019
Solar project G0634, Kittitas County
Solar
80.0 MWWithdrawn / abandoned Kittitas, WAWest Dec 2019target 2021
Onshore wind project G0552, Pacific County
Onshore wind
80.0 MWWithdrawn / abandoned Pacific, WAWest Aug 2016target 2019
Cielo Wind Power
Onshore wind · Cielo Wind Power
80.0 MWWithdrawn / abandoned Klickitat, WAWest Sep 2001target 2003
Solar project 90, Kittitas County
Solar
80.0 MWWithdrawn / abandoned Kittitas, WAWest Aug 2020target 2023
Pacific Winds Inc
Onshore wind · Pacific Winds, Inc.
76.0 MWWithdrawn / abandoned Benton, WAWest Sep 2000target 2002
Pacific Winds Inc
Onshore wind · Pacific Winds, Inc.
76.0 MWWithdrawn / abandoned Benton, WAWest Aug 2000target 2002
Onshore wind project G0249, Klickitat County
Onshore wind
75.0 MWWithdrawn / abandoned Klickitat, WAWest Dec 2006target 2008
Onshore wind project 8, Adams County
Onshore wind
75.0 MWWithdrawn / abandoned Adams, WAWest Nov 2007target 2010
Energy Northwest Inc
Onshore wind
75.0 MWWithdrawn / abandoned Benton, WAWest Jun 2002target 2004
Solar project G0393, Kittitas County
Solar
75.0 MWWithdrawn / abandoned Kittitas, WAWest Nov 2009target 2010
Onshore wind project 5, Whitman County
Onshore wind
75.0 MWWithdrawn / abandoned Whitman, WAWest Jul 2007target 2009
Onshore wind project G0210, Lincoln County
Onshore wind
75.0 MWWithdrawn / abandoned Lincoln, WAWest Sep 2005target 2006
Onshore wind project G0278, Klickitat County
Onshore wind
75.0 MWWithdrawn / abandoned Klickitat, WAWest Jul 2007target 2009
Solar project G0612, Klickitat County
Solar
75.0 MWWithdrawn / abandoned Klickitat, WAWest Jan 2019target 2021
Solar project 67, Kittitas County
Solar
74.9 MWWithdrawn / abandoned Kittitas, WAWest Sep 2018target 2020
Onshore wind project 14, Columbia County
Onshore wind · PacifiCorp Commercial & Trading
70.2 MWWithdrawn / abandoned Columbia, WAWest Sep 2001target 2005
Solar project CS24-11, Whitman County
Solar
70.0 MWWithdrawn / abandoned Whitman, WAWest Apr 2024target 2027
Hydro project G0496, Pend Oreille County
Hydro
70.0 MWWithdrawn / abandoned Pend Oreille, WAWest Dec 2013target 2014
Other project G0378, Mason County
Other
65.0 MWWithdrawn / abandoned Mason, WAWest Aug 2009target 2012
Other project G0371, Grays Harbor County
Other
65.0 MWWithdrawn / abandoned Grays Harbor, WAWest Jun 2009target 2012
Onshore wind project G0369, Benton County
Onshore wind
65.0 MWWithdrawn / abandoned Benton, WAWest Jun 2009target 2012
Hydro project 93, Skagit County
Hydro
63.0 MWWithdrawn / abandoned Skagit, WAWest Dec 2020target 2022
Solar project G0705, Benton County
Solar
60.0 MWWithdrawn / abandoned Benton, WAWest Sep 2021target 2024
Solar project 923, Walla Walla County
Solar
60.0 MWWithdrawn / abandoned Walla Walla, WAWest Aug 2017target 2019
Other project 658, Clark County
Other · OR Solar 4, LLC
60.0 MWWithdrawn / abandoned Clark, WAWest Apr 2015target 2016
Solar project G1073, Benton County
Solar
60.0 MWWithdrawn / abandoned Benton, WAWest Sep 2024target 2026
Gas project G0495, Clark County
Gas
60.0 MWWithdrawn / abandoned Clark, WAWest Dec 2013target 2016
Onshore wind project G0396, Klickitat County
Onshore wind
56.0 MWWithdrawn / abandoned Klickitat, WAWest Nov 2009target 2013
Solar + storage project CS25-06, Grant County
Solar + storage
54.0 MWWithdrawn / abandoned Grant, WAWest Apr 2025target 2031
Gas project G0575, Grays Harbor County
Gas
51.0 MWWithdrawn / abandoned Grays Harbor, WAWest Sep 2017target 2018
Onshore wind project G0322, Klickitat County
Onshore wind
51.0 MWWithdrawn / abandoned Klickitat, WAWest Apr 2008target 2009
Onshore wind project G0375, Klickitat County
Onshore wind
50.0 MWWithdrawn / abandoned Klickitat, WAWest Jul 2009target 2011
Onshore wind project 11, Lincoln County
Onshore wind
50.0 MWWithdrawn / abandoned Lincoln, WAWest Jan 2008target 2011
50MW Alcoa-St Johns
Gas · Calpine Energy Services, L.P.
50.0 MWWithdrawn / abandoned Clark, WAWest Feb 2001target 2001
Onshore wind project 1, Lincoln County
Onshore wind
50.0 MWWithdrawn / abandoned Lincoln, WAWest Dec 2003target 2005
Other project G0364, Kittitas County
Other
50.0 MWWithdrawn / abandoned Kittitas, WAWest Apr 2009target 2011
Onshore wind project 30, Whitman County
Onshore wind
50.0 MWWithdrawn / abandoned Whitman, WAWest Dec 2010target 2013
50MW Alcoa
Gas · Calpine Energy Services, L.P.
50.0 MWWithdrawn / abandoned Clark, WAWest Apr 2001target 2001
Gas project 64, Skagit County
Gas
46.7 MWWithdrawn / abandoned Skagit, WAWest Aug 2018target 2018
Gas project 68, Skagit County
Gas
46.7 MWWithdrawn / abandoned Skagit, WAWest Sep 2018target 2019
Gas project 69, Skagit County
Gas
46.7 MWWithdrawn / abandoned Skagit, WAWest Sep 2018target 2019
Solar project G0627, Klickitat County
Solar
45.0 MWWithdrawn / abandoned Klickitat, WAWest Jul 2019target 2021
GNA Energy
Gas · GNA Energy, LLC
45.0 MWWithdrawn / abandoned Klickitat, WAWest May 2001target 2002
Onshore wind project 22, Lincoln County
Onshore wind
40.0 MWWithdrawn / abandoned Lincoln, WAWest Aug 2009target 2011
Solar project 54, Adams County
Solar
40.0 MWWithdrawn / abandoned Adams, WAWest May 2017target 2019
Battery storage project C2-192, Yakima County
Battery storage
40.0 MWWithdrawn / abandoned Yakima, WAWest May 2022target 2027
Battery storage project C2-193, Yakima County
Battery storage
40.0 MWWithdrawn / abandoned Yakima, WAWest May 2022target 2027
Solar + storage project C2-195, Yakima County
Solar + storage
40.0 MWWithdrawn / abandoned Yakima, WAWest May 2022target 2027
Page 8 of 10

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)