United States › Grid › Interconnection queues › Washington
ONSHORE WIND · WESTPacific Winds Inc
Pacific Winds Inc is a 76.0 MW onshore wind request withdrawn in the West interconnection queue, in Benton County, Washington, connecting to Pacific Winds, Inc..
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2000 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G11
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Pacific Winds, Inc.
- Developer
- Pacific Winds, Inc.
- Connection point (POI)
- a new POR in the vicinity of the Franklin-McNary 230 kV line
- Location
- Benton County, Washington
- Technology
- Wind: 76.0 MW
- Total requested
- 76.0 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 13 September 2000
- Proposed online date
- July 2002
Location
Marker shows the centre of Benton County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Benton County
- Solar + storage project G0822, Benton CountySolar + storage · 4,000 MW · in study
- Nuclear project G0998, Benton CountyNuclear · 1,120 MW · in study
- Solar + storage project G0670, Benton CountySolar + storage · 1,000 MW · in study
- Solar + storage project G0688, Benton CountySolar + storage · 1,000 MW · in study
- Solar + storage project G1040, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G0932, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G1037, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G1039, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G0920, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G0933, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G1038, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G0684, Benton CountySolar + storage · 705 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem