πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

ONSHORE WIND Β· WEST

Onshore wind project 1, Lincoln County

Onshore wind project 1, Lincoln County is a 50.0 MW onshore wind request withdrawn in the West interconnection queue, in Lincoln County, Washington, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2003 (completed)
  2. Withdrawn / abandonedMay 2006 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Devils Gap-Lind 115 kV
Location
Lincoln County, Washington
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
11 December 2003
Proposed online date
December 2005
Withdrawn
May 2006

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem