Onshore wind project 11, Lincoln County

Onshore wind project 11, Lincoln County is a 50.0 MW onshore wind request withdrawn in the West interconnection queue, in Lincoln County, Washington, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2008 (completed)
  2. Withdrawn / abandonedMar 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
11
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Devils Gap-Lind 115 kV
Location
Lincoln County, Washington
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
2 January 2008
Proposed online date
December 2011
Withdrawn
March 2010

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.