Onshore wind project 8, Adams County

Onshore wind project 8, Adams County is a 75.0 MW onshore wind request withdrawn in the West interconnection queue, in Adams County, Washington, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2007 (completed)
  2. Withdrawn / abandonedMar 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
8
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Benton-Othello 115 kV
Location
Adams County, Washington
Technology
Wind: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
27 November 2007
Proposed online date
October 2010
Withdrawn
March 2013

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem