🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Texas — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,486351.5 GW
Active in queue476.4 GW2,094 requests
Agreement signed124.6 GW606 requests
Withdrawn917184.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,486 requests · page 8 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3045, Orange County
Solar
300 MWIn study Orange, TXMISO Sep 2022target 2026
Wisdom Solar SLF
Solar + storage · Wisdom Green Energy LLC
299 MWIn study Pecos, TXERCOT Feb 2025target 2027
Barranca Wind 2
Onshore wind · Barranca Wind Energy, LLC
299 MWIn study Jim Hogg, TXERCOT Jul 2025target 2028
Camino Ranch Storage SLF
Solar + storage · Camino Solar Ranch, LLC
298 MWIn study Houston, TXERCOT Oct 2022target 2028
Palo Verde Wind
Wind + storage · RWE Clean Energy Development, LLC
298 MWIn study San Patricio, TXERCOT Apr 2024target 2027
Camino Ranch Solar SLF
Solar + storage · Camino Ranch Solar Project LLC
296 MWIn study Houston, TXERCOT Oct 2022target 2028
Columbine Wind
Onshore wind · Wilson Wind LLC
295 MWIn study Gonzales, TXERCOT Feb 2025target 2029
Sanders Hollow Energy Center
Onshore wind · Sanders Hollow Energy Center, LLC
293 MWIn study Dickens, TXERCOT Oct 2024target 2028
Vista Bluff Wind 2
Onshore wind
290 MWPaused / redesign Upton, TXERCOT Sep 2024
Vista Bluff Wind 1
Onshore wind
290 MWPaused / redesign Upton, TXERCOT Sep 2024
Vista Bluff Wind II "Alternate POI"
Onshore wind · Vista Bluff Windpower, LLC
290 MWIn study Upton, TXERCOT Sep 2025target 2029
Vista Bluff Wind I "Alternate POI"
Onshore wind · Vista Bluff Windpower, LLC
290 MWIn study Upton, TXERCOT Sep 2025target 2029
Tres Rios Ranch BESS
Solar + storage · LectricWind LLC
290 MWIn study Upton, TXERCOT May 2023target 2027
Shifting Gale Wind
Onshore wind
289 MWPaused / redesign Castro, TXERCOT Apr 2018target 2025
Onshore wind project J3902, Jefferson County
Onshore wind
289 MWIn study Jefferson, TXMISO Feb 2025target 2028
Sandow Solar
Solar · Sandow Lakes Ranch Solar I, LLC
287 MWIn study Milam, TXERCOT Sep 2020target 2028
Baker Branch BESS
Battery storage · Mockingbird Storage Center, LLC
287 MWIn study Lamar, TXERCOT Jun 2025target 2029
Inadale BESS
Solar + storage · Inadale BESS, LLC
287 MWIn study Scurry, TXERCOT Feb 2023target 2028
Fierce River BESS
Solar + storage · Rio Grande Solar LLC
285 MWIn study Starr, TXERCOT Mar 2024target 2029
Fivemile Wind
Onshore wind · Longview Wind, LLC
282 MWIn study Dawson, TXERCOT Apr 2025target 2028
Impala Flats Wind
Onshore wind · Antelope Flats Wind, LLC
282 MWIn study Lynn, TXERCOT Jan 2019target 2026
Treehouse Solar
Solar + storage · Treehouse Solar, LLC
282 MWIn study Grimes, TXERCOT Jul 2025target 2028
Jukebox Solar
Solar · ACE DevCo NC, LLC
281 MWIn study Frio, TXERCOT Jun 2025target 2027
Inadale Solar
Solar + storage · Inadale Solar, LLC
281 MWIn study Scurry, TXERCOT Feb 2023target 2028
Solar + storage project GEN-2024-015, Yoakum County
Solar + storage
280 MWIn study Yoakum, TXSPP Oct 2024target 2028
Unicorn BESS
Battery storage · Unicorn Energies
279 MWIn study Fort Bend, TXERCOT Jan 2024target 2027
Pease River Solar
Solar · Pease River Solar LLC
276 MWIn study Foard, TXERCOT Dec 2025target 2029
Blue Hills Wind
Onshore wind
276 MWPaused / redesign Val Verde, TXERCOT May 2019target 2026
Roboman Solar
Solar · Roboman Solar, LLC
273 MWIn study Coke, TXERCOT Jul 2025target 2029
Solar project J3986, Liberty County
Solar
270 MWIn study Liberty, TXMISO Oct 2024target 2030
Santa Garcias Solar
Solar · Oxy Renewable Energy LLC
265 MWIn study Kleberg, TXERCOT Jun 2023target 2028
Possum Kingdom Solar
Solar + storage · PK Solar, LLC
262 MWIn study Jack, TXERCOT Sep 2021target 2027
Charolais Solar
Solar + storage · RWE Solar Development, LLC
262 MWIn study Matagorda, TXERCOT Aug 2019target 2026
Velociraptor BESS II
Solar + storage · Greyhound BESS 3 LLC
261 MWIn study Ector, TXERCOT May 2025target 2028
Velociraptor BESS I
Solar + storage · Greyhound BESS 2 LLC
261 MWIn study Ector, TXERCOT May 2025target 2028
Verily Solar (FKA Cuello De Cuero Solar)
Solar · NextEra Energy Interconnection Holdings, LLC
261 MWIn study Brooks, TXERCOT Mar 2024target 2029
Homestead Power (TEF-Due Diligence)
Gas · Homestead Power LLC
260 MWIn study Austin, TXERCOT Jul 2024target 2029
Ochoa Energy Storage
Battery storage · Ochoa Energy Storage LLC
260 MWIn study Waller, TXERCOT Apr 2023target 2027
Jay Flat BESS
Battery storage · Jay Flat BESS LLC
259 MWIn study Kent, TXERCOT Jan 2025target 2029
Horsepower BESS
Battery storage · Horsepower BESS, LLC
258 MWIn study Bexar, TXERCOT Dec 2025target 2028
Masava Storage
Battery storage · Savannah Oaks Solar Project, LLC
257 MWIn study Madison, TXERCOT Sep 2022target 2028
Saddlehorn Energy Storage
Battery storage · Saddlehorn, LLC
257 MWIn study Austin, TXERCOT Nov 2024target 2028
Van Zandt Energy Storage
Battery storage · Rocky Mountain Energy Holdings, LLC
257 MWIn study Ector, TXERCOT Jun 2023target 2027
Shamrock II Wind
Onshore wind
257 MWPaused / redesign Crockett, TXERCOT Jul 2023target 2028
Rex Storage
Battery storage · Rex BESS, LLC
256 MWIn study Harris, TXERCOT Jun 2024target 2027
Bell County Morgan Storage
Battery storage · DM-BCTRM, LLC
256 MWIn study Bell, TXERCOT Nov 2024target 2028
Sunburst BESS
Solar + storage · Indigo Solar, LLC
256 MWIn study San Patricio, TXERCOT Oct 2024target 2029
Nautilus Heavy Storage
Battery storage · Nautilus Heavy Storage, LLC
256 MWIn study San Patricio, TXERCOT Dec 2023target 2028
Leaning Tree BESS
Battery storage
256 MWPaused / redesign Throckmorton, TXERCOT Nov 2023target 2026
Maleza Storage II
Battery storage · Brush Storage, LLC
256 MWIn study Wharton, TXERCOT Feb 2024target 2027
Page 8 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)