Completed queue projects in PJM (Mid-Atlantic, Midwest) — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,19297.6 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,192 requests · page 8 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Oak Trail Solar
Solar
50.0 MWOperating Currituck, NCPJM Mar 20192023
High Point Solar
Solar
50.0 MWOperating Stephenson, ILPJM Mar 20182023
Powells Creek Solar
Solar
50.0 MWOperating Halifax, VAPJM Mar 20172023
Sandy Ridge WF
Onshore wind
50.0 MWOperating Centre, PAPJM Apr 20062012
Buckeye Plains Solar
Solar
49.9 MWOperating Pickaway, OHPJM Nov 20162025
Pickaway County II Solar
Solar
49.9 MWOperating Pickaway, OHPJM Sep 20162025
Bluestone Farm Solar
Solar
49.9 MWOperating Mecklenburg, VAPJM Feb 20162021
Clinton Solar
Solar
49.9 MWOperating Clinton, OHPJM Dec 20172025
Pickaway County Solar
Solar
49.9 MWOperating Pickaway, OHPJM Sep 20162025
Blue Harvest Solar Park
Solar
49.9 MWOperating Putnam, OHPJM Sep 20172023
Buckeye Plains II Solar
Solar
49.9 MWOperating Pickaway, OHPJM Nov 20162025
Salt City Solar
Solar
49.9 MWOperating Ross, OHPJM May 20162023
Timber Road Solar Park
Solar
49.9 MWOperating Paulding, OHPJM Sep 20172024
Montpelier Solar
Solar
49.0 MWOperating Williams, OHPJM Mar 20192025
Hog Creek Wind Farm
Onshore wind
48.3 MWOperating Hardin, OHPJM Apr 20082017
Beaver Valley Power Station
Nuclear
48.0 MWOperating Beaver, PAPJM Oct 20082013
Lee Energy Facility
Gas
48.0 MWOperating Lee, ILPJM Oct 20162018
Fayette Solar
Solar
48.0 MWOperating Fayette, OHPJM Jun 20182025
South Boston Energy Facility
Other
47.4 MWOperating Halifax, VAPJM Jun 20102013
Linden Generating Station
Gas
47.0 MWOperating Union, NJPJM Feb 20132016
University Park North Energy Center
Gas
46.0 MWOperating Will, ILPJM Mar 20172023
Alton Post Office Solar
Solar
45.9 MWOperating Halifax, VAPJM Aug 20172025
Kingsport Mill
Other
45.0 MWOperating Sullivan, TNPJM Jul 20142017
Fayette Energy Facility
Gas
45.0 MWOperating Fayette, PAPJM Apr 20152017
Washington Energy Facility
Gas
45.0 MWOperating Washington, OHPJM Apr 20152016
Gas project Y3-107, Bergen County
Gas
45.0 MWOperating Bergen, NJPJM Apr 20132015
Newark Energy Center
Gas
45.0 MWOperating Essex, NJPJM Jun 20122015
Cornu
Gas
45.0 MWOperating Lawrence, OHPJM Apr 20152016
Clearview Solar I
Solar
45.0 MWOperating Champaign, OHPJM Aug 20192025
Cornu
Gas
45.0 MWOperating Lawrence, OHPJM Apr 20152016
Halifax County Solar
Solar
44.7 MWOperating Halifax, VAPJM Nov 20162024
Linden 1 & 2
Gas
44.0 MWOperating Union, NJPJM Oct 20072008
Archbald
Gas
44.0 MWOperating Lackawanna, PAPJM Dec 19982001
Beaver Valley Power Station
Nuclear
43.0 MWOperating Beaver, PAPJM Oct 20082012
Hope Creek 1
Nuclear
43.0 MWOperating Salem, NJPJM Jan 20022007
Sycamore Solar I
Solar
42.0 MWOperating Pittsylvania, VAPJM Sep 20162023
Bethlehem Gen Facility Units 1 - 8
Gas
42.0 MWOperating Northampton, PAPJM Sep 20072009
SPSA Navy Power Plant
Other
40.0 MWOperating City Of Portsmouth, VAPJM May 20122014
Troy Energy
Gas
40.0 MWOperating Wood, OHPJM Apr 20102014
Smithton Generating Station
Gas
40.0 MWOperating Westmoreland, PAPJM Oct 20152018
St. Joseph's Energy Center, LLC
Gas
40.0 MWOperating St. Joseph, INPJM Sep 20152018
Kearny Generating Station
Gas
40.0 MWOperating Hudson, NJPJM Feb 20132015
Rockford I Energy Center
Gas
40.0 MWOperating Winnebago, ILPJM Mar 20172021
Arche Energy Project
Solar
40.0 MWOperating Fulton, OHPJM Aug 20192024
Casselman WF1
Onshore wind
40.0 MWOperating Somerset, PAPJM Dec 20032007
Lincoln Generating Facility
Gas
40.0 MWOperating Will, ILPJM Oct 20082013
Ontelaunee Power Generating Plant
Gas
38.9 MWOperating Berks, PAPJM Jan 20182019
Onshore wind project Y1-033, Somerset County
Onshore wind
38.3 MWOperating Somerset, PAPJM Feb 20122016
Mount Storm Unit 2
Coal
38.0 MWOperating Grant, WVPJM Jul 20072011
Mount Storm Unit 1
Coal
38.0 MWOperating Grant, WVPJM Jul 20072013
Page 8 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)