ONSHORE WIND · PJM

Sandy Ridge WF

Sandy Ridge WF is a 50.0 MW onshore wind request built and operating in the PJM interconnection queue, in Centre County, Pennsylvania, connecting to PENELEC.

Queue statusOperating
  1. PlanningQueued Apr 2006 (completed)
  2. ConsentedMay 2021 (completed)
  3. Construction (completed)
  4. OperatingApr 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q36
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Philipsburg - Tyrone North 115kV
Location
Centre County, Pennsylvania
Technology
Wind: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
28 April 2006
Agreement signed
12 May 2021
Proposed online date
December 2011
Came online
April 2012

Location

Marker shows the centre of Centre County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Centre County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem