United States βΊ Grid βΊ Interconnection queues βΊ Ohio
GAS Β· PJMCornu
Cornu is a 45.0 MW gas request built and operating in the PJM interconnection queue, in Lawrence County, Ohio, connecting to AEP.
Request details
- Queue ID
- AA2-137
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Hanging Rock 765kV - Power Block 1
- Location
- Lawrence County, Ohio
- Technology
- Gas: 45.0 MW
- Total requested
- 45.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 30 April 2015
- Proposed online date
- May 2019
- Came online
- December 2016
Location
Marker shows the centre of Lawrence County; the queue data does not give exact sites.
Other requests in Lawrence County
- Gas project AH1-686, Lawrence CountyGas Β· 24.0 MW Β· in study
- CornuGas Β· 45.0 MW Β· built
- Hanging Rock CC2Gas Β· 20.0 MW Β· built
- CornuGas Β· 10.0 MW Β· built
- Other project L01_AEP137, Lawrence CountyOther Β· 165 MW Β· withdrawn
- South PointOther Β· 20.0 MW Β· withdrawn
- Battery storage project Y3-096, Lawrence CountyBattery storage Β· 10.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem