United States › Grid › Interconnection queues › Utah

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Utah — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown64684.7 GW
Active in queue33.8 GW154 requests
Agreement signed4,095 MW25 requests
Withdrawn64684.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

646 requests · page 7 of 13
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project C3-117, Duchesne County
Solar
100 MWWithdrawn / abandoned Duchesne, UTWest May 2023target 2028
Solar + storage project C2-124, Millard County
Solar + storage
100 MWWithdrawn / abandoned Millard, UTWest May 2022target 2025
Solar + storage project C3-058, Carbon County
Solar + storage
100 MWWithdrawn / abandoned Carbon, UTWest May 2023target 2026
Solar + storage project C3-127, Kane County
Solar + storage
100 MWWithdrawn / abandoned Kane, UTWest May 2023target 2027
Solar + storage project 1024, Cache County
Solar + storage
100 MWWithdrawn / abandoned Cache, UTWest May 2018target 2020
Solar project PIS019, Tooele County
Solar · PacifiCorp
99.0 MWWithdrawn / abandoned Tooele, UTWest Jun 2022target 2025
Solar project 254, Iron County
Solar
90.0 MWWithdrawn / abandoned Iron, UTWest Dec 2008target 2011
Battery storage project 1117, Salt Lake County
Battery storage
90.0 MWWithdrawn / abandoned Salt Lake, UTWest Feb 2019target 2021
Solar + storage project C2-202, Millard County
Solar + storage
90.0 MWWithdrawn / abandoned Millard, UTWest May 2022target 2026
Solar project 821, Carbon County
Solar
87.0 MWWithdrawn / abandoned Carbon, UTWest Nov 2016target 2018
Battery storage project C2-138, Salt Lake County
Battery storage
85.0 MWWithdrawn / abandoned Salt Lake, UTWest May 2022target 2026
Battery storage project PIS055, Salt Lake County
Battery storage
85.0 MWWithdrawn / abandoned Salt Lake, UTWest Mar 2024target 2027
Solar + storage project C3-123, Carbon County
Solar + storage
85.0 MWWithdrawn / abandoned Carbon, UTWest May 2023target 2027
Solar project 683, Beaver County
Solar
80.0 MWWithdrawn / abandoned Beaver, UTWest Jul 2015target 2016
Solar project 587, Emery County
Solar
80.0 MWWithdrawn / abandoned Emery, UTWest Jul 2014target 2016
Onshore wind project 221-B, Summit County
Onshore wind
80.0 MWWithdrawn / abandoned Summit, UTWest May 2008target 2011
Solar project 800, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Sep 2016target 2019
Onshore wind project 416, San Juan County
Onshore wind
80.0 MWWithdrawn / abandoned San Juan, UTWest Mar 2012target 2014
Solar project 601, Emery County
Solar
80.0 MWWithdrawn / abandoned Emery, UTWest Aug 2014target 2016
Solar project 813, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Oct 2016target 2019
Onshore wind project 221-A, Summit County
Onshore wind
80.0 MWWithdrawn / abandoned Summit, UTWest May 2008target 2010
Onshore wind project 128, Beaver County
Onshore wind · Clipper Windpower Development Company, Inc
80.0 MWWithdrawn / abandoned Beaver, UTWest Mar 2007target 2009
Solar project 588, San Juan County
Solar
80.0 MWWithdrawn / abandoned San Juan, UTWest Jul 2014target 2016
Onshore wind project 868, Rich County
Onshore wind
80.0 MWWithdrawn / abandoned Rich, UTWest Apr 2017target 2019
Onshore wind project 867, Carbon County
Onshore wind
80.0 MWWithdrawn / abandoned Carbon, UTWest Apr 2017target 2019
Solar project 610, Juab County
Solar
80.0 MWWithdrawn / abandoned Juab, UTWest Aug 2014target 2016
Solar project 541, San Juan County
Solar
80.0 MWWithdrawn / abandoned San Juan, UTWest Dec 2013target 2015
Solar + storage project TCS-17, Rich County
Solar + storage
80.0 MWWithdrawn / abandoned Rich, UTWest Nov 2018target 2023
Solar project 591, Juab County
Solar
80.0 MWWithdrawn / abandoned Juab, UTWest Jul 2014target 2016
Battery storage project C2-133, Juab County
Battery storage
80.0 MWWithdrawn / abandoned Juab, UTWest May 2022target 2026
Onshore wind project 474, Washington County
Onshore wind
80.0 MWWithdrawn / abandoned Washington, UTWest Mar 2013target 2014
Solar project 1086, Tooele County
Solar
80.0 MWWithdrawn / abandoned Tooele, UTWest Nov 2018target 2021
Solar project 574, Tooele County
Solar
80.0 MWWithdrawn / abandoned Tooele, UTWest Jun 2014target 2015
Solar project 575, Salt Lake County
Solar
80.0 MWWithdrawn / abandoned Salt Lake, UTWest Jun 2014target 2015
Onshore wind project 218-A, Iron County
Onshore wind
80.0 MWWithdrawn / abandoned Iron, UTWest May 2008target 2010
Onshore wind project 400, San Juan County
Onshore wind · PacifiCorp Energy
80.0 MWWithdrawn / abandoned San Juan, UTWest Sep 2011target 2013
Solar project 798, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Sep 2016target 2019
Battery storage project PIS032, Juab County
Battery storage
80.0 MWWithdrawn / abandoned Juab, UTWest Apr 2023target 2026
Solar project 814, Iron County
Solar
80.0 MWWithdrawn / abandoned Iron, UTWest Nov 2016target 2018
Onshore wind project 418, San Juan County
Onshore wind
80.0 MWWithdrawn / abandoned San Juan, UTWest Mar 2012target 2014
Solar project 602, Sevier County
Solar
80.0 MWWithdrawn / abandoned Sevier, UTWest Aug 2014target 2016
Solar project 996, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Dec 2017target 2020
Solar + storage project 1083, Rich County
Solar + storage
80.0 MWWithdrawn / abandoned Rich, UTWest Nov 2018target 2023
Solar + storage project TCS-22, Rich County
Solar + storage
80.0 MWWithdrawn / abandoned Rich, UTWest Dec 2018target 2022
Solar project 782, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Aug 2016target 2018
Solar + storage project 1094, Rich County
Solar + storage
80.0 MWWithdrawn / abandoned Rich, UTWest Dec 2018target 2023
Solar + storage project C3-143, Sevier County
Solar + storage
80.0 MWWithdrawn / abandoned Sevier, UTWest May 2023target 2028
Solar project 812, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Oct 2016target 2019
Onshore wind project 426, San Juan County
Onshore wind
79.9 MWWithdrawn / abandoned San Juan, UTWest Jun 2012
Onshore wind project 420-A, San Juan County
Onshore wind
79.2 MWWithdrawn / abandoned San Juan, UTWest Mar 2012target 2014
Page 7 of 13

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)