ONSHORE WIND Β· WESTOnshore wind project 221-A, Summit County
Onshore wind project 221-A, Summit County is a 80.0 MW onshore wind request withdrawn in the West interconnection queue, in Summit County, Utah, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2008 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 221-A
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Thief Creek - Evanston substations
- Location
- Summit County, Utah
- Technology
- Wind: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- REMOVED-LACK OF PROGRESS
- Queue status
- Withdrawn
- Entered queue
- 20 May 2008
- Proposed online date
- December 2010
Location
Marker shows the centre of Summit County; the queue data does not give exact sites.
Other requests in Summit County
- Onshore wind project 786, Summit CountyOnshore wind Β· 100 MW Β· agreement signed
- Onshore wind project 221-B, Summit CountyOnshore wind Β· 80.0 MW Β· withdrawn
- Onshore wind project 221-C, Summit CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Solar project S0019, Summit CountySolar Β· 50.0 MW Β· withdrawn
- Onshore wind project 1005, Summit CountyOnshore wind Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem