United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR Β· WEST

Solar project 254, Iron County

Solar project 254, Iron County is a 90.0 MW solar request withdrawn in the West interconnection queue, in Iron County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
254
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Enterprise - Moyle line.
Location
Iron County, Utah
Technology
Solar: 90.0 MW
Total requested
90.0 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
18 December 2008
Proposed online date
August 2011

Location

Marker shows the centre of Iron County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Iron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem