ONSHORE WIND Β· WEST

Onshore wind project 128, Beaver County

Onshore wind project 128, Beaver County is a 80.0 MW onshore wind request withdrawn in the West interconnection queue, in Beaver County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2007 (completed)
  2. Withdrawn / abandonedApr 2013 (project stopped here)
  3. ConsentedMar 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
128
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Clipper Windpower Development Company, Inc
Connection point (POI)
Near Cove Fort substation
Location
Beaver County, Utah
Technology
Wind: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
IA signed 3/12/10, Suspended 4/21/10, IA Terminated 4/21/13
Queue status
Withdrawn
Entered queue
13 March 2007
Agreement signed
12 March 2010
Proposed online date
November 2009
Withdrawn
April 2013

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Beaver County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem