Battery storage project PIS032, Juab County

Battery storage project PIS032, Juab County is a 80.0 MW battery storage request withdrawn in the West interconnection queue, in Juab County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
PIS032
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Mona substation
Location
Juab County, Utah
Technology
Battery: 80.0 MW
Total requested
80.0 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
14 April 2023
Proposed online date
December 2026

Location

Marker shows the centre of Juab County; the queue data does not give exact sites.