Withdrawn queue requests in Arkansas — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown32457.8 GW
Active in queue35.4 GW157 requests
Agreement signed1,783 MW13 requests
Withdrawn32457.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

324 requests · page 7 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J2828, Pulaski County
Solar + storage
50.0 MWWithdrawn / abandoned Pulaski, ARMISO Sep 2022target 2025
Solar project J3218, Nevada County
Solar
50.0 MWWithdrawn / abandoned Nevada, ARMISO Sep 2022target 2025
Battery storage project J3001, Pulaski County
Battery storage
50.0 MWWithdrawn / abandoned Pulaski, ARMISO Sep 2022target 2025
Solar project J393, Arkansas County
Solar
49.0 MWWithdrawn / abandoned Arkansas, ARMISO Sep 2014
Solar project J894, Woodruff County
Solar
45.0 MWWithdrawn / abandoned Woodruff, ARMISO Jun 2017target 2020
Gas project J508, Clark County
Gas
42.7 MWWithdrawn / abandoned Clark, ARMISO Nov 2015target 2017
Solar project J690, Lonoke County
Solar
42.0 MWWithdrawn / abandoned Lonoke, ARMISO Jul 2016target 2018
Battery storage project J2006, Arkansas County
Battery storage
40.0 MWWithdrawn / abandoned Arkansas, ARMISO Aug 2021target 2025
Battery storage project J2994, Arkansas County
Battery storage
40.0 MWWithdrawn / abandoned Arkansas, ARMISO Sep 2022target 2025
Solar project J377, Bradley County
Solar
40.0 MWWithdrawn / abandoned Bradley, ARMISO Jul 2014
Battery storage project J1250, Clay County
Battery storage
35.0 MWWithdrawn / abandoned Clay, ARMISO Apr 2019target 2022
Solar project GEN-2016-166, Washington County
Solar
35.0 MWWithdrawn / abandoned Washington, ARSPP Nov 2016target 2019
Solar project J895, Lonoke County
Solar
33.0 MWWithdrawn / abandoned Lonoke, ARMISO Jun 2017target 2020
Other project J685, Clark County
Other
30.0 MWWithdrawn / abandoned Clark, ARMISO Jul 2016target 2017
Solar project J347, Craighead County
Solar
30.0 MWWithdrawn / abandoned Craighead, ARMISO May 2014
Battery storage project J1293, Lee County
Battery storage
25.0 MWWithdrawn / abandoned Lee, ARMISO Apr 2019target 2022
Battery storage project J1484, Union County
Battery storage
25.0 MWWithdrawn / abandoned Union, ARMISO Apr 2019target 2023
Solar project GEN-2017-003, Little River County
Solar
21.6 MWWithdrawn / abandoned Little River, ARSPP Jan 2017target 2018
Solar project GEN-2017-002, Sebastian County
Solar
21.6 MWWithdrawn / abandoned Sebastian, ARSPP Jan 2017target 2018
Onshore wind project GEN-2010-025, Benton County
Onshore wind
20.0 MWWithdrawn / abandoned Benton, ARSPP Mar 2010target 2010
Solar project J507, Pulaski County
Solar
16.7 MWWithdrawn / abandoned Pulaski, ARMISO Nov 2015target 2016
Solar + storage project J1648, Searcy County
Solar + storage
10.0 MWWithdrawn / abandoned Searcy, ARMISO Jun 2020target 2021
Battery storage project J1723, Cross County
Battery storage
10.0 MWWithdrawn / abandoned Cross, ARMISO Nov 2021target 2023
Solar project J1789, Monroe County
Solar
6.0 MWWithdrawn / abandoned Monroe, ARMISO Jun 2020target 2021
Page 7 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)