GAS Β· MISOGas project J508, Clark County
Gas project J508, Clark County is a 42.7 MW gas request withdrawn in the MISO interconnection queue, in Clark County, Arkansas, connecting to Entergy.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2015 (completed)
- Withdrawn / abandonedJul 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J508
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Entergy
- Connection point (POI)
- tap 115 kV line betwwen W Arkadelphia sub and Delarc sub at 3.85 miles from West Arkadelphia substat
- Location
- Clark County, Arkansas
- Technology
- Gas: 42.7 MW
- Total requested
- 42.7 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 November 2015
- Proposed online date
- April 2017
- Withdrawn
- July 2017
Location
Marker shows the centre of Clark County; the queue data does not give exact sites.
Other requests in Clark County
- Solar project J3304, Clark CountySolar Β· 350 MW Β· withdrawn
- Solar + storage project J3658, Clark CountySolar + storage Β· 150 MW Β· withdrawn
- Solar project J688, Clark CountySolar Β· 92.0 MW Β· withdrawn
- Solar project J2636, Clark CountySolar Β· 78.5 MW Β· withdrawn
- Other project J685, Clark CountyOther Β· 30.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem