Gas project J508, Clark County

Gas project J508, Clark County is a 42.7 MW gas request withdrawn in the MISO interconnection queue, in Clark County, Arkansas, connecting to Entergy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2015 (completed)
  2. Withdrawn / abandonedJul 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J508
Grid region
MISO (Midcontinent)
Utility / transmission owner
Entergy
Connection point (POI)
tap 115 kV line betwwen W Arkadelphia sub and Delarc sub at 3.85 miles from West Arkadelphia substat
Location
Clark County, Arkansas
Technology
Gas: 42.7 MW
Total requested
42.7 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 November 2015
Proposed online date
April 2017
Withdrawn
July 2017

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.