United States βΊ Grid βΊ Interconnection queues βΊ Arkansas
SOLAR + STORAGE Β· MISOSolar + storage project J3658, Clark County
Solar + storage project J3658, Clark County is a 150 MW solar + storage request withdrawn in the MISO interconnection queue, in Clark County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2024 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3658
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- GURDON - BEIRNE 115.0kV
- Location
- Clark County, Arkansas
- Technology
- Solar: 150 MW Β· Battery
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 25 March 2024
- Proposed online date
- June 2028
- Withdrawn
- December 2025
Location
Marker shows the centre of Clark County; the queue data does not give exact sites.
Other requests in Clark County
- Solar project J3304, Clark CountySolar Β· 350 MW Β· withdrawn
- Solar project J688, Clark CountySolar Β· 92.0 MW Β· withdrawn
- Solar project J2636, Clark CountySolar Β· 78.5 MW Β· withdrawn
- Gas project J508, Clark CountyGas Β· 42.7 MW Β· withdrawn
- Other project J685, Clark CountyOther Β· 30.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem