United States βΊ Grid βΊ Interconnection queues βΊ Arkansas
SOLAR Β· SPPSolar project GEN-2017-002, Sebastian County
Solar project GEN-2017-002, Sebastian County is a 21.6 MW solar request withdrawn in the SPP interconnection queue, in Sebastian County, Arkansas, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2017 (completed)
- Withdrawn / abandonedNov 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2017-002
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Huntington 69 kV sub
- Location
- Sebastian County, Arkansas
- Technology
- Solar: 21.6 MW
- Total requested
- 21.6 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 31 January 2017
- Proposed online date
- December 2018
- Withdrawn
- November 2017
Location
Marker shows the centre of Sebastian County; the queue data does not give exact sites.
Other requests in Sebastian County
- Battery storage project GEN-2022-130, Sebastian CountyBattery storage Β· 200 MW Β· in study
- Battery storage project GEN-2023-206, Sebastian CountyBattery storage Β· 50.0 MW Β· in study
- Gas project GEN-2000-006, Sebastian CountyGas Β· 660 MW Β· withdrawn
- Gas project GEN-2000-012, Sebastian CountyGas Β· 660 MW Β· withdrawn
- Solar project GEN-2023-180, Sebastian CountySolar Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem