| Project | Capacity | Status |
|---|---|---|
| Battery storage project AH1-730, City Of Suffolk County Battery storage · SolAmerica Energy, LLC |
100 MW | Withdrawn / abandoned |
| Solar project AE1-220, Nelson County Solar |
100 MW | Withdrawn / abandoned |
| Solar + storage project AG2-523, Prince George County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project AH1-119, Frederick County Solar + storage |
100 MW | Withdrawn / abandoned |
| Battery storage project AH1-750, Prince Edward County Battery storage · Pine Lake Solar LLC |
100 MW | Withdrawn / abandoned |
| Solar + storage project AE1-248, Southampton County Solar + storage |
100 MW | Withdrawn / abandoned |
| Battery storage project AG2-620, Fauquier County Battery storage |
100 MW | Withdrawn / abandoned |
| Bella Terra Solar |
100 MW | Withdrawn / abandoned |
| Energix Westmoreland LLC Solar · Energix Westmoreland, LLC |
100 MW | Withdrawn / abandoned |
| Sugar Solar LLC Solar · Sugar Solar, LLC |
100 MW | Withdrawn / abandoned |
| Solar project AD2-207, Isle Of Wight County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project AG1-019, King George County Battery storage · Harwood Power, LLC |
100 MW | Withdrawn / abandoned |
| Battery storage project AG2-303, King George County Battery storage |
100 MW | Withdrawn / abandoned |
| Sand Dragon Energy Battery storage · Sand Dragon Energy LLC |
100 MW | Withdrawn / abandoned |
| Solar project AH1-651, Southampton County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project AG2-324, Loudoun County Battery storage |
100 MW | Withdrawn / abandoned |
| Onshore wind project U2-050, Tazewell County Onshore wind |
100 MW | Withdrawn / abandoned |
| Battery storage project AG2-268, Halifax County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar project AF1-246, Charlotte County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project AG2-307, Loudoun County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar project AC2-094, Louisa County Solar |
99.9 MW | Withdrawn / abandoned |
| Solar project AH1-381, Bedford County Solar |
99.5 MW | Withdrawn / abandoned |
| Solar + storage project AF1-059, Mecklenburg County Solar + storage |
99.2 MW | Withdrawn / abandoned |
| Onshore wind project Y1-029, Accomack County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project AC1-227, Botetourt County Onshore wind |
96.6 MW | Withdrawn / abandoned |
| Onshore wind project W3-054A, Accomack County Onshore wind |
95.0 MW | Withdrawn / abandoned |
| Solar project AG2-168, Russell County Solar |
95.0 MW | Withdrawn / abandoned |
| Solar project AE2-196, Wythe County Solar |
94.6 MW | Withdrawn / abandoned |
| Solar + storage project AG2-604, Montgomery County Solar + storage |
94.0 MW | Withdrawn / abandoned |
| Solar project AF2-037, Louisa County Solar · AURA POWER DEVELOPMENTS (USA), LLC |
94.0 MW | Withdrawn / abandoned |
| Solar project AE2-233, Accomack County Solar |
94.0 MW | Withdrawn / abandoned |
| Solar project AF1-031, Caroline County Solar |
93.5 MW | Withdrawn / abandoned |
| Gas project AH1-717, Surry County Gas · Virginia Electric and Power Company |
92.7 MW | Withdrawn / abandoned |
| Tidewater Solar Projects Solar |
91.0 MW | Withdrawn / abandoned |
| Solar + storage project AG2-584, Frederick County Solar + storage |
90.0 MW | Withdrawn / abandoned |
| Summersweet Energy Center, LLC Battery storage · Summersweet Energy Center, LLC |
90.0 MW | Withdrawn / abandoned |
| Solar + storage project AH1-092, Halifax County Solar + storage · Scarlet Oak Solar, LLC |
90.0 MW | Withdrawn / abandoned |
| Antlers Road Solar Solar · RWE Solar Development, LLC |
90.0 MW | Withdrawn / abandoned |
| Battery storage project AG1-240, Botetourt County Battery storage |
90.0 MW | Withdrawn / abandoned |
| Other project U2-056 Other |
88.7 MW | Withdrawn / abandoned |
| Solar project AG2-461, New Kent County Solar |
88.0 MW | Withdrawn / abandoned |
| Solar project AG2-508, Greensville County Solar |
85.0 MW | Withdrawn / abandoned |
| Solar project AC2-082, Fauquier County Solar |
85.0 MW | Withdrawn / abandoned |
| Solar project AE1-109A, Southampton County Solar |
85.0 MW | Withdrawn / abandoned |
| Solar project AG2-521, Fluvanna County Solar |
85.0 MW | Withdrawn / abandoned |
| Solar project AB2-039, Southampton County Solar |
85.0 MW | Withdrawn / abandoned |
| Solar + storage project AG2-427, Sussex County Solar + storage · Old Forty Road Solar, LLC |
85.0 MW | Withdrawn / abandoned |
| Solar + storage project AC1-206, Greensville County Solar + storage |
85.0 MW | Withdrawn / abandoned |
| Round Hill Solar Solar |
83.0 MW | Withdrawn / abandoned |
| Solar project AE1-130, Bedford County Solar |
83.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)