United States › Grid › Interconnection queues › Virginia
SOLAR · PJMTidewater Solar Projects
Tidewater Solar Projects is a 91.0 MW solar request withdrawn in the PJM interconnection queue, in Southampton County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2015 (completed)
- Withdrawn / abandonedJan 2022 (project stopped here)
- ConsentedMar 2022 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AB2-015
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Franklin 115kV
- Location
- Southampton County, Virginia
- Technology
- Solar: 91.0 MW
- Total requested
- 91.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 21 December 2015
- Agreement signed
- 31 March 2022
- Proposed online date
- December 2022
- Withdrawn
- January 2022
Location
Marker shows the centre of Southampton County; the queue data does not give exact sites.
Other requests in Southampton County
- Battery storage project AJ1-019, Southampton CountyBattery storage · 100 MW · in study
- Newsoms SolarSolar · 100 MW · built
- Battery storage project AH2-225, Southampton CountyBattery storage · 125 MW · withdrawn
- Solar project AC2-105, Southampton CountySolar · 100 MW · withdrawn
- Solar project AH1-652, Southampton CountySolar · 100 MW · withdrawn
- Solar + storage project AE1-248, Southampton CountySolar + storage · 100 MW · withdrawn
- Solar project AH1-651, Southampton CountySolar · 100 MW · withdrawn
- Solar project AE1-109A, Southampton CountySolar · 85.0 MW · withdrawn
- Solar project AB2-039, Southampton CountySolar · 85.0 MW · withdrawn
- Solar project AB2-171, Southampton CountySolar · 75.0 MW · withdrawn
- Solar project AD2-090, Southampton CountySolar · 70.0 MW · withdrawn
- Solar + storage project AG1-343, Southampton CountySolar + storage · 62.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem