United States βΊ Grid βΊ Interconnection queues βΊ Virginia
SOLAR Β· PJMSolar project AD2-090, Southampton County
Solar project AD2-090, Southampton County is a 70.0 MW solar request withdrawn in the PJM interconnection queue, in Southampton County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedJan 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AD2-090
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Handsom - Southampton 115kV
- Location
- Southampton County, Virginia
- Technology
- Solar: 70.0 MW
- Total requested
- 70.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 20 March 2018
- Proposed online date
- December 2020
- Withdrawn
- January 2020
Location
Marker shows the centre of Southampton County; the queue data does not give exact sites.
Other requests in Southampton County
- Battery storage project AJ1-019, Southampton CountyBattery storage Β· 100 MW Β· in study
- Newsoms SolarSolar Β· 100 MW Β· built
- Battery storage project AH2-225, Southampton CountyBattery storage Β· 125 MW Β· withdrawn
- Solar project AC2-105, Southampton CountySolar Β· 100 MW Β· withdrawn
- Solar project AH1-652, Southampton CountySolar Β· 100 MW Β· withdrawn
- Solar + storage project AE1-248, Southampton CountySolar + storage Β· 100 MW Β· withdrawn
- Solar project AH1-651, Southampton CountySolar Β· 100 MW Β· withdrawn
- Tidewater Solar ProjectsSolar Β· 91.0 MW Β· withdrawn
- Solar project AE1-109A, Southampton CountySolar Β· 85.0 MW Β· withdrawn
- Solar project AB2-039, Southampton CountySolar Β· 85.0 MW Β· withdrawn
- Solar project AB2-171, Southampton CountySolar Β· 75.0 MW Β· withdrawn
- Solar + storage project AG1-343, Southampton CountySolar + storage Β· 62.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem