🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › North Dakota

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in North Dakota — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown28555.0 GW
Active in queue14.5 GW63 requests
Agreement signed2,129 MW13 requests
Withdrawn28555.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

285 requests · page 6 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Coal project G607, Mercer County
Coal
25.0 MWWithdrawn / abandoned Mercer, NDMISO Mar 2006target 2007
Onshore wind project MPC01100, Cass County
Onshore wind
20.0 MWWithdrawn / abandoned Cass, NDMISO Mar 2008target 2008
Onshore wind project G993, Kidder County
Onshore wind
20.0 MWWithdrawn / abandoned Kidder, NDMISO Mar 2008target 2016
Coal project GI-0210, Mercer County
Coal
20.0 MWWithdrawn / abandoned Mercer, NDWest Jun 2002
Onshore wind project G446, Lamoure County
Onshore wind
19.5 MWWithdrawn / abandoned Lamoure, NDMISO Sep 2004
Onshore wind project G981, Grant County
Onshore wind
19.5 MWWithdrawn / abandoned Grant, NDMISO Mar 2008target 2011
Onshore wind project G284, Dickey County
Onshore wind
19.0 MWWithdrawn / abandoned Dickey, NDMISO Jan 2003target 2003
Other project G277, Dickey County
Other
19.0 MWWithdrawn / abandoned Dickey, NDMISO Dec 2002target 2003
Onshore wind project G283, Mcintosh County
Onshore wind
19.0 MWWithdrawn / abandoned Mcintosh, NDMISO Jan 2003target 2003
Onshore wind project G311, Bowman County
Onshore wind
19.0 MWWithdrawn / abandoned Bowman, NDMISO Mar 2003target 2004
Onshore wind project G248, Dickey County
Onshore wind
19.0 MWWithdrawn / abandoned Dickey, NDMISO Aug 2002target 2003
Onshore wind project G312, Dickey County
Onshore wind
19.0 MWWithdrawn / abandoned Dickey, NDMISO Mar 2003target 2003
Onshore wind project G307, Mcintosh County
Onshore wind
19.0 MWWithdrawn / abandoned Mcintosh, NDMISO Mar 2003target 2004
Onshore wind project G308, Mcintosh County
Onshore wind
19.0 MWWithdrawn / abandoned Mcintosh, NDMISO Mar 2003target 2004
Onshore wind project G313, Dickey County
Onshore wind
19.0 MWWithdrawn / abandoned Dickey, NDMISO Mar 2003target 2008
Other project H035, Bowman County
Other
15.0 MWWithdrawn / abandoned Bowman, NDMISO May 2008target 2011
Gas project GI-0721, Williams County
Gas
14.5 MWWithdrawn / abandoned Williams, NDWest Nov 2007target 2009
Onshore wind project GEN-2016-066, Stark County
Onshore wind
13.0 MWWithdrawn / abandoned Stark, NDSPP Mar 2016target 2016
Onshore wind project G328, Mchenry County
Onshore wind
12.0 MWWithdrawn / abandoned Mchenry, NDMISO Apr 2003target 2003
Other project G151, Mcintosh County
Other
12.0 MWWithdrawn / abandoned Mcintosh, NDMISO Nov 2001target 2002
Onshore wind project MPC03100, Cass County
Onshore wind
11.9 MWWithdrawn / abandoned Cass, NDMISO Nov 2016target 2018
Other project G710, Mcintosh County
Other
10.0 MWWithdrawn / abandoned Mcintosh, NDMISO Dec 2006target 2010
Other project GI-0614b, Morton County
Other
10.0 MWWithdrawn / abandoned Morton, NDWest Sep 2006
Onshore wind project MPC03200, Cass County
Onshore wind
9.6 MWWithdrawn / abandoned Cass, NDMISO Nov 2016target 2018
Onshore wind project MPC03400, Cavalier County
Onshore wind
9.5 MWWithdrawn / abandoned Cavalier, NDMISO Dec 2016target 2018
Onshore wind project GEN-2016-065, Stark County
Onshore wind
6.8 MWWithdrawn / abandoned Stark, NDSPP Mar 2016target 2016
Onshore wind project J766, Oliver County
Onshore wind
3.8 MWWithdrawn / abandoned Oliver, NDMISO Nov 2016target 2018
Onshore wind project GEN-2016-053, Burleigh County
Onshore wind
3.3 MWWithdrawn / abandoned Burleigh, NDSPP Mar 2016target 2016
Onshore wind project GEN-2016-052, Burleigh County
Onshore wind
3.3 MWWithdrawn / abandoned Burleigh, NDSPP Mar 2016target 2016
Onshore wind project MPC03500, Cavalier County
Onshore wind
3.2 MWWithdrawn / abandoned Cavalier, NDMISO Dec 2016target 2018
Gas project GI-1107, Divide County
Gas
2.0 MWWithdrawn / abandoned Divide, NDWest Nov 2011target 2012
Onshore wind project GEN-2016-155, Burleigh County
Onshore wind
1.3 MWWithdrawn / abandoned Burleigh, NDSPP Nov 2016target 2017
Onshore wind project G450, Rolette County
Onshore wind
1.0 MWWithdrawn / abandoned Rolette, NDMISO Aug 2004target 2006
Onshore wind project MPC03300, Cass County
Onshore wind
0.8 MWWithdrawn / abandoned Cass, NDMISO Nov 2016target 2018
Gas project GI-1010, Burke County
Gas
0.8 MWWithdrawn / abandoned Burke, NDWest Oct 2010target 2011
Page 6 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)