United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project G981, Grant County

Onshore wind project G981, Grant County is a 19.5 MW onshore wind request withdrawn in the MISO interconnection queue, in Grant County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2008 (completed)
  2. Withdrawn / abandonedNov 2011 (project stopped here)
  3. ConsentedNov 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G981
Grid region
MISO (Midcontinent)
Connection point (POI)
New IC owned sbstn tapping into a 69kV MDU line at N46? 19' 8" / W101? 54' 45"
Location
Grant County, North Dakota
Technology
Wind: 19.5 MW
Total requested
19.5 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
10 March 2008
Agreement signed
15 November 2011
Proposed online date
December 2011
Withdrawn
November 2011

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem