United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project G446, Lamoure County

Onshore wind project G446, Lamoure County is a 19.5 MW onshore wind request withdrawn in the MISO interconnection queue, in Lamoure County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2004 (completed)
  2. Withdrawn / abandonedJul 2005 (project stopped here)
  3. ConsentedJul 2005 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G446
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Lamoure County, North Dakota
Technology
Wind: 19.5 MW
Total requested
19.5 MW
Queue status
Withdrawn
Entered queue
2 September 2004
Agreement signed
13 July 2005
Withdrawn
July 2005

Location

Marker shows the centre of Lamoure County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Lamoure County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem