Onshore wind project G311, Bowman County

Onshore wind project G311, Bowman County is a 19.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Bowman County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2003 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedJul 2004 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G311
Grid region
MISO (Midcontinent)
Connection point (POI)
Gascoyne Jct. 34.5 kV substation
Location
Bowman County, North Dakota
Technology
Wind: 19.0 MW
Total requested
19.0 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
19 March 2003
Agreement signed
12 July 2004
Proposed online date
March 2004

Location

Marker shows the centre of Bowman County; the queue data does not give exact sites.