πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· MISO

Onshore wind project G810, Bowman County

Onshore wind project G810, Bowman County is a 101 MW onshore wind request withdrawn in the MISO interconnection queue, in Bowman County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2007 (completed)
  2. Withdrawn / abandonedMay 2011 (project stopped here)
  3. ConsentedMay 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G810
Grid region
MISO (Midcontinent)
Connection point (POI)
Hettinger 115 kV substation
Location
Bowman County, North Dakota
Technology
Wind: 101 MW
Total requested
101 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
14 June 2007
Agreement signed
4 May 2011
Proposed online date
December 2009
Withdrawn
May 2011

Location

Marker shows the centre of Bowman County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Bowman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem