United States › Grid › Interconnection queues › North Dakota
ONSHORE WIND · MISOOnshore wind project J003, Bowman County
Onshore wind project J003, Bowman County is a 20.0 MW onshore wind request built and operating in the MISO interconnection queue, in Bowman County, North Dakota.
Request details
- Queue ID
- J003
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- 132N, 105W, Section 23 NE 1/4
- Location
- Bowman County, North Dakota
- Technology
- Wind: 20.0 MW
- Total requested
- 20.0 MW
- Study phase
- DPP - SIS
- Queue status
- Operational
- Entered queue
- 22 October 2008
- Agreement signed
- 28 April 2010
- Proposed online date
- April 2005
- Came online
- April 2005
Location
Marker shows the centre of Bowman County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Bowman County
- Onshore wind project GEN-2017-010, Bowman CountyOnshore wind · 200 MW · built
- Coal project G712, Bowman CountyCoal · 513 MW · withdrawn
- Other project G110, Bowman CountyOther · 500 MW · withdrawn
- Solar project GEN-2020-006, Bowman CountySolar · 250 MW · withdrawn
- Onshore wind project J755, Bowman CountyOnshore wind · 200 MW · withdrawn
- Solar project GEN-2022-078, Bowman CountySolar · 180 MW · withdrawn
- Onshore wind project G810, Bowman CountyOnshore wind · 101 MW · withdrawn
- Onshore wind project J018, Bowman CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project G311, Bowman CountyOnshore wind · 19.0 MW · withdrawn
- Other project H035, Bowman CountyOther · 15.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem