πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

COAL Β· MISO

Coal project G712, Bowman County

Coal project G712, Bowman County is a 513 MW coal request withdrawn in the MISO interconnection queue, in Bowman County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2006 (completed)
  2. Withdrawn / abandonedDec 2008 (project stopped here)
  3. ConsentedDec 2008 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G712
Grid region
MISO (Midcontinent)
Connection point (POI)
existing unnamed 230 kV transmission line 2 miles south of plant
Location
Bowman County, North Dakota
Technology
Coal: 513 MW
Total requested
513 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
11 December 2006
Agreement signed
1 December 2008
Proposed online date
October 2012
Withdrawn
December 2008

Location

Marker shows the centre of Bowman County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Bowman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem