OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Massachusetts — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown37048.3 GW
Active in queue11.2 GW35 requests
Agreement signed6,013 MW17 requests
Withdrawn37048.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

370 requests · page 6 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Eversource Group @ Cross Rd 651
Solar + storage
9.5 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2020target 2023
EE Group @ Doreen
Solar + storage
9.1 MWWithdrawn / abandoned Berkshire, MAISO-NE Jun 2023target 2024
Battery Storage
Battery storage
9.1 MWWithdrawn / abandoned Franklin, MAISO-NE Sep 2022target 2027
Webster St - NG Western MA Area Cluster Study
Solar
9.0 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2018target 2020
East Longmeadow substation - NG Western MA Area Cluster Study
Solar
9.0 MWWithdrawn / abandoned Hampden, MAISO-NE Mar 2019target 2022
Group @ French King - WMA ASO
Solar + storage
8.9 MWWithdrawn / abandoned Franklin, MAISO-NE Jan 2022target 2023
Group @ Maynard 416 - EMA ASO
Solar + storage
8.5 MWWithdrawn / abandoned Middlesex, MAISO-NE Jan 2022target 2023
Solar
Solar
8.1 MWWithdrawn / abandoned Worcester, MAISO-NE Nov 2018target 2020
E. Westminster Substation - NG Western MA Area Cluster Study
Solar
8.0 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2018target 2022
Eversource Group @ Falmouth 993
Solar + storage
8.0 MWWithdrawn / abandoned Barnstable, MAISO-NE Apr 2020target 2023
EE Valley DG Group Study
Solar
8.0 MWWithdrawn / abandoned Plymouth, MAISO-NE Nov 2023target 2026
Crystal Lake Substation - NG WMA Group 3
Battery storage
8.0 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2026
Combined Reciprocating, Solar and Battery modification
Solar + storage
7.8 MWWithdrawn / abandoned Middlesex, MAISO-NE Sep 2018target 2022
Group @ Berkshire 18C
Solar + storage
7.7 MWWithdrawn / abandoned Hampden, MAISO-NE Jan 2022target 2023
Group @ Podick - WMA ASO
Solar + storage
7.7 MWWithdrawn / abandoned Hampden, MAISO-NE Jan 2022target 2023
Wind
Onshore wind
7.5 MWWithdrawn / abandoned Berkshire, MAISO-NE Jun 2018target 2020
Eversource Group @ Crystal Spring 646
Solar + storage
7.5 MWWithdrawn / abandoned Middlesex, MAISO-NE Apr 2020target 2023
Eversource Group @ Arsene St 654
Solar + storage
7.0 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2020target 2023
Group @ Blandford 19J - WMA ASO
Solar + storage
7.0 MWWithdrawn / abandoned Berkshire, MAISO-NE Jan 2022target 2023
Group @ West Pond 737 - EMA ASO
Solar + storage
7.0 MWWithdrawn / abandoned Middlesex, MAISO-NE Jun 2022target 2025
EE Group @ Southwick
Solar + storage
7.0 MWWithdrawn / abandoned Hampden, MAISO-NE Jun 2023target 2024
Uxbridge Substation – NG Hopedale West Group Study
Battery storage
7.0 MWWithdrawn / abandoned Worcester, MAISO-NE Sep 2022target 2025
Group @ Duxbury 738 - EMA ASO
Solar + storage
6.8 MWWithdrawn / abandoned Plymouth, MAISO-NE Jun 2022target 2023
Little Rest Rd Substation - NG Western MA Area Cluster Study
Solar
6.0 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2018target 2022
Solar
Solar
6.0 MWWithdrawn / abandoned Bristol, MAISO-NE Mar 2011target 2012
Little Rest Rd Substation - NG WMA Group 3
Solar + storage
5.8 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Solar + battery
Solar + storage
5.5 MWWithdrawn / abandoned Middlesex, MAISO-NE Apr 2020target 2025
Eversource Group Study @ Wing Lane
Solar
5.1 MWWithdrawn / abandoned Bristol, MAISO-NE Mar 2020target 2023
NG NEMA Group DER Study
Solar + storage
5.0 MWWithdrawn / abandoned Essex, MAISO-NE Dec 2023target 2025
EE 2024 SEMA/Cape ASO Group Study
Solar + storage
5.0 MWWithdrawn / abandoned Plymouth, MAISO-NE May 2024target 2026
Solar + Battery
Solar + storage
5.0 MWWithdrawn / abandoned Norfolk, MAISO-NE Apr 2020target 2023
EE 2024 SEMA/Cape ASO Group Study
Solar + storage
5.0 MWWithdrawn / abandoned Bristol, MAISO-NE May 2024target 2026
Individual @ Montague
Battery storage
5.0 MWWithdrawn / abandoned Franklin, MAISO-NE Jun 2023target 2024
Canton 470 - EMA ASO
Solar + storage
5.0 MWWithdrawn / abandoned Norfolk, MAISO-NE Jun 2022target 2023
Walpole 146 110A - 2023 EE GB ASO
Solar + storage
5.0 MWWithdrawn / abandoned Norfolk, MAISO-NE Jan 2024target 2026
Holliston 130 - EMA ASO
Battery storage
5.0 MWWithdrawn / abandoned Middlesex, MAISO-NE Jan 2022target 2023
RMLD DER Group Study
Battery storage
5.0 MWWithdrawn / abandoned Middlesex, MAISO-NE Jul 2024target 2025
NG NEMA Group DER Study
Battery storage
5.0 MWWithdrawn / abandoned Middlesex, MAISO-NE Dec 2023target 2025
EE 2024 SEMA/Cape ASO Group Study
Battery storage
5.0 MWWithdrawn / abandoned Plymouth, MAISO-NE May 2024target 2026
EE 2024 SEMA/Cape ASO Group Study
Solar + storage
5.0 MWWithdrawn / abandoned Plymouth, MAISO-NE May 2024target 2024
Tremont 713 - EMA ASO
Solar + storage
5.0 MWWithdrawn / abandoned Plymouth, MAISO-NE Jun 2022target 2025
Cumberland 22B - WMA ASO
Solar + storage
5.0 MWWithdrawn / abandoned Hampden, MAISO-NE Jan 2022target 2023
Solar
Solar
5.0 MWWithdrawn / abandoned Norfolk, MAISO-NE Jan 2019target 2021
Royalston Substation - NG WMA Group 3
Solar + storage
5.0 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
EE 2024 SEMA/Cape ASO Group Study
Solar + storage
5.0 MWWithdrawn / abandoned Bristol, MAISO-NE May 2024target 2026
EE 2024 SEMA/Cape ASO Group Study
Battery storage
5.0 MWWithdrawn / abandoned Plymouth, MAISO-NE May 2024target 2024
Hyannis 961 - EMA ASO
Solar + storage
5.0 MWWithdrawn / abandoned Barnstable, MAISO-NE Jun 2022target 2023
Ashburnham substation - NG Western MA Area Cluster Study
Solar
5.0 MWWithdrawn / abandoned Worcester, MAISO-NE Mar 2019target 2023
EE 2024 SEMA/Cape ASO Group Study
Solar + storage
5.0 MWWithdrawn / abandoned Plymouth, MAISO-NE May 2024target 2026
E. Westminster Substation - NG WMA Group 3
Solar + storage
5.0 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2026

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)