United States › Grid › Interconnection queues › Massachusetts
SOLAR + STORAGE · ISO-NEEversource Group @ Crystal Spring 646
Eversource Group @ Crystal Spring 646 is a 7.5 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Middlesex County, Massachusetts.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2020 (completed)
- Withdrawn / abandonedJun 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 997
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Eversource Crystal Spring 646
- Location
- Middlesex County, Massachusetts
- Technology
- Solar: 7.5 MW · Battery
- Total requested
- 7.5 MW
- Queue status
- Withdrawn
- Entered queue
- 9 April 2020
- Proposed online date
- November 2023
- Withdrawn
- June 2025
Location
Marker shows the centre of Middlesex County; the queue data does not give exact sites.
Power plants in Massachusetts · Transmission lines in Massachusetts
Other requests in Middlesex County
- Battery StorageBattery storage · 508 MW · agreement signed
- Norman Street Battery StorageBattery storage · 204 MW · agreement signed
- Battery StorageBattery storage · 500 MW · in study
- Battery StorageBattery storage · 125 MW · in study
- Kendall Revised Reconfiguration ProjectGas · 250 MW · built
- L'EnergiaGas · 74.0 MW · built
- Cogen DGGas · 43.0 MW · built
- Combined Reciprocating, Solar and BatterySolar + storage · 7.8 MW · built
- Kendall #3 Back Pressure Steam TurbineGas · 7.5 MW · built
- Kendall Reconfiguration ProjectGas · 1.9 MW · built
- Battery StorageBattery storage · 500 MW · withdrawn
- Billerica PowerGas · 311 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem