United States βΊ Grid βΊ Interconnection queues βΊ Massachusetts
SOLAR Β· ISO-NESolar
Solar is a 8.1 MW solar request withdrawn in the ISO-NE interconnection queue, in Worcester County, Massachusetts, connecting to NGRID.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2018 (completed)
- Withdrawn / abandonedJun 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 797
- Grid region
- ISO-NE (New England)
- Utility / transmission owner
- NGRID
- Connection point (POI)
- GRID P7 and P8 McCormick Rd/Meadow St 552L5 (Spencer, MA)
- Location
- Worcester County, Massachusetts
- Technology
- Solar: 8.1 MW
- Total requested
- 8.1 MW
- Queue status
- Withdrawn
- Entered queue
- 5 November 2018
- Proposed online date
- December 2020
- Withdrawn
- June 2025
Location
Marker shows the centre of Worcester County; the queue data does not give exact sites.
Power plants in Massachusetts Β· Transmission lines in Massachusetts
Other requests in Worcester County
- Battery StorageBattery storage Β· 204 MW Β· agreement signed
- Battery StorageBattery storage Β· 300 MW Β· in study
- Battery StorageBattery storage Β· 180 MW Β· in study
- Combined Cycle Uprate #2Gas Β· 30.0 MW Β· built
- Crystal Lake Substation - NG Western MA Area Cluster StudySolar Β· 24.7 MW Β· built
- Solar with BatterySolar + storage Β· 10.0 MW Β· built
- Harrington Street PV Project (QF)Solar Β· 9.8 MW Β· built
- Litchfield substation - NG Western MA Area Cluster StudySolar Β· 9.5 MW Β· built
- N. Oxford Substation - NG Western MA Area Cluster StudySolar Β· 8.7 MW Β· built
- SolarSolar Β· 8.0 MW Β· built
- Fitchburg Renewable EnergyOther Β· 7.2 MW Β· built
- SolarSolar Β· 6.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem