ONSHORE WIND Β· ISO-NEWind
Wind is a 7.5 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Berkshire County, Massachusetts.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2018 (completed)
- Withdrawn / abandonedAug 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 769
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Eversource 23 kV Feeder Berkshire Substation
- Location
- Berkshire County, Massachusetts
- Technology
- Wind: 7.5 MW
- Total requested
- 7.5 MW
- Queue status
- Withdrawn
- Entered queue
- 13 June 2018
- Proposed online date
- March 2020
- Withdrawn
- August 2018
Location
Marker shows the centre of Berkshire County; the queue data does not give exact sites.
Power plants in Massachusetts Β· Transmission lines in Massachusetts
Other requests in Berkshire County
- Bear Swamp Unit 1 and 2 UpgradeBattery storage Β· 66.0 MW Β· agreement signed
- Berkshire Wind IncreaseOnshore wind Β· 4.6 MW Β· agreement signed
- Battery StorageBattery storage Β· 290 MW Β· in study
- Battery StorageBattery storage Β· 170 MW Β· in study
- Battery StorageBattery storage Β· 136 MW Β· in study
- Bear Swamp Pump Load increaseBattery storage Β· 333 MW Β· built
- Bear Swamp Pumping Load IncreaseBattery storage Β· 333 MW Β· built
- Altresco Increase (winter)Gas Β· 193 MW Β· built
- Hoosac Wind ProjectOnshore wind Β· 28.5 MW Β· built
- Berkshire Wind Power ProjectOnshore wind Β· 15.0 MW Β· built
- Syncarpha Blandford Solar plus battery storageSolar + storage Β· 5.0 MW Β· built
- Bear Swamp Upper Yard substation - NG Western MA Area Cluster StudySolar Β· 2.5 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem