| Project | Capacity | Status |
|---|---|---|
| Solar + storage project J3747, Lonoke County Solar + storage |
300 MW | Withdrawn / abandoned |
| Battery storage project J3264, Otsego County Battery storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project J3262, Jefferson County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project J3640, Shiawassee County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project J3307, Callaway County Solar |
300 MW | Withdrawn / abandoned |
| Coopers Corner BESS Battery storage ยท ACE DevCo NC,LLC |
300 MW | Withdrawn / abandoned |
| Onshore wind project C4-106, Bingham County Onshore wind |
300 MW | Withdrawn / abandoned |
| Battery storage project J3693, Marshall County Battery storage |
300 MW | Withdrawn / abandoned |
| Gas project J3407, Manistee County Gas |
300 MW | Withdrawn / abandoned |
| Battery storage project 631, Hendry County Battery storage ยท FPL |
300 MW | Withdrawn / abandoned |
| Solar project J3878, Jefferson County Solar |
300 MW | Withdrawn / abandoned |
| Solar project IC-1236, Charlton County Solar |
300 MW | Withdrawn / abandoned |
| Solar + storage project C4-040, Millard County Solar + storage |
300 MW | Withdrawn / abandoned |
| Genovia Storage Battery storage ยท Genovia Storage LLC |
300 MW | Withdrawn / abandoned |
| Cedar Lake Storage Battery storage ยท Emeren US, LLC |
300 MW | Withdrawn / abandoned |
| Battery storage project J3810, Knox County Battery storage |
300 MW | Withdrawn / abandoned |
| Battery storage project J3362, Oakland County Battery storage |
300 MW | Withdrawn / abandoned |
| Battery storage project J3460, St. Clair County Battery storage |
290 MW | Withdrawn / abandoned |
| Solar project 956594, Pamlico County Solar ยท Masked |
290 MW | Withdrawn / abandoned |
| Oyster shore Energy storage Battery storage ยท Shore Rd ESS LLC |
275 MW | Withdrawn / abandoned |
| Millwood Energy Storage Battery storage ยท 82 Shingle House Rd, LLC |
274 MW | Withdrawn / abandoned |
| Battery storage project Q2411, Pinal County Battery storage |
271 MW | Withdrawn / abandoned |
| Sentinel Solar Solar ยท Alamo Ranch Solar Project, LLC |
271 MW | Withdrawn / abandoned |
| Solar project J3773, Drew County Solar |
265 MW | Withdrawn / abandoned |
| Battery storage project J3537, Kalamazoo County Battery storage |
265 MW | Withdrawn / abandoned |
| Gas project J3553, Adair County Gas |
263 MW | Withdrawn / abandoned |
| Replacing 261 MW Coal with 615 MW Solar; Edwards Unit 2 Other |
261 MW | Withdrawn / abandoned |
| Holbrook Energy Storage II Battery storage ยท Holbrook Energy Storage, LLC |
260 MW | Withdrawn / abandoned |
| Mill Run BESS Battery storage ยท Renew Development HoldCo LLC |
260 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
254 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
251 MW | Withdrawn / abandoned |
| Battery storage project J3354, Clinton County Battery storage |
250 MW | Withdrawn / abandoned |
| Kce NY 32 Battery storage ยท KCE NY 38, LLC |
250 MW | Withdrawn / abandoned |
| Battery storage project J3259, Renville County Battery storage |
250 MW | Withdrawn / abandoned |
| Ball Hill BESS Battery storage ยท Northland Power U.S. Projects Inc |
250 MW | Withdrawn / abandoned |
| Solar project J3571, Poinsett County Solar |
250 MW | Withdrawn / abandoned |
| Battery storage project J3248, Posey County Battery storage |
250 MW | Withdrawn / abandoned |
| Solar + storage project GI-TC-2024-13, Routt County Solar + storage |
250 MW | Withdrawn / abandoned |
| Onshore wind project LGE-GIS-2024-007, Harlan County Onshore wind |
250 MW | Withdrawn / abandoned |
| Solar project J3415, Mercer County Solar |
250 MW | Withdrawn / abandoned |
| Solar project J3568, Leflore County Solar |
250 MW | Withdrawn / abandoned |
| Solar + storage project J3769, Saginaw County Solar + storage |
250 MW | Withdrawn / abandoned |
| Solar + storage project J3746, Grant Parish County Solar + storage |
250 MW | Withdrawn / abandoned |
| Solar project GEN-2024-057, Cass County Solar |
250 MW | Withdrawn / abandoned |
| Solar + storage project J3593, Clay County Solar + storage |
250 MW | Withdrawn / abandoned |
| Solar project J3455, Trinity County Solar |
250 MW | Withdrawn / abandoned |
| Battery storage project J3360, Morgan County Battery storage |
250 MW | Withdrawn / abandoned |
| Battery storage project J3824, Roberts County Battery storage |
250 MW | Withdrawn / abandoned |
| Solar project J3768, Walker County Solar |
250 MW | Withdrawn / abandoned |
| Solar project IC-1238, Wilcox County Solar |
250 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)411 ยท 78.5 GW
- NYISO (New York)294 ยท 63.3 GW
- West (non-ISO utilities)237 ยท 46.1 GW
- Southeast (non-ISO utilities)195 ยท 32.8 GW
- ISO-NE (New England)97 ยท 13.2 GW
- ERCOT (Texas)50 ยท 10.0 GW
- SPP (Southwest Power Pool)29 ยท 7,503 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)