OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2021 requests) โ€” page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,149339.1 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,149 requests ยท page 5 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2174, Tunica County
Solar
390 MWWithdrawn / abandoned Tunica, MSMISO Aug 2021target 2025
Offshore wind Increase (QP909)
Offshore wind
386 MWWithdrawn / abandoned MAISO-NE Apr 2021target 2027
Norte Vista
Solar + storage
386 MWWithdrawn / abandoned Fresno, CACAISO Apr 2021target 2024
Solar + storage project TCS-15, Adams County
Solar + storage
375 MWWithdrawn / abandoned Adams, WAWest Jan 2021target 2024
Onshore wind project GI-2021-25, Morgan County
Onshore wind
362 MWWithdrawn / abandoned Morgan, COWest Oct 2021target 2024
Olivos
Battery storage
360 MWWithdrawn / abandoned CACAISO Apr 2021target 2024
Solar + storage project 9, Sacramento County
Solar + storage
360 MWWithdrawn / abandoned Sacramento, CAWest Mar 2021target 2023
Offshore wind project AH1-556, Monmouth County
Offshore wind
360 MWWithdrawn / abandoned Monmouth, NJPJM Sep 2021target 2029
Live Oak Storage
Battery storage
358 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2024
Brenda Renewable Energy Complex
Solar
358 MWWithdrawn / abandoned La Paz, AZCAISO Apr 2021target 2025
Boxcar Solar
Solar ยท EDF Renewables Development, Inc.
356 MWWithdrawn / abandoned ERCOT Mar 2021target 2027
Solar + storage project AG2-414, Henry County
Solar + storage
350 MWWithdrawn / abandoned Henry, VAPJM Mar 2021target 2025
Replace 350 MW of ALTW.FPL_DAEC Unit with Solar; Duane Arnold
Other
350 MWWithdrawn / abandoned Otter Tail, MNMISO Feb 2021target 2023
Solar project J2194, Sullivan County
Solar
350 MWWithdrawn / abandoned Sullivan, INMISO Aug 2021target 2024
Solar project J2175, Washington County
Solar
350 MWWithdrawn / abandoned Washington, MSMISO Aug 2021target 2025
Andromeda
Solar + storage
346 MWWithdrawn / abandoned Tulare, CACAISO Apr 2021target 2029
Other project AG2-556, Vigo County
Other
339 MWWithdrawn / abandoned Vigo, INPJM Mar 2021target 2024
Increase to Pumping load
Battery storage
333 MWWithdrawn / abandoned Berkshire, MAISO-NE Nov 2021target 2021
Solar project AG2-684, Metcalfe County
Solar
331 MWWithdrawn / abandoned Metcalfe, KYPJM Mar 2021target 2024
Solar project AG2-466
Solar ยท Hobet Solar I, LLC
330 MWWithdrawn / abandoned WVPJM Mar 2021target 2024
Battery Storage
Battery storage
325 MWWithdrawn / abandoned Windham, CTISO-NE Nov 2021target 2028
Christoval Solar
Solar ยท Bridgelink Cave Springs LLC
324 MWWithdrawn / abandoned Tom Green, TXERCOT Feb 2021target 2024
Onshore wind project J2241, Benton County
Onshore wind
320 MWWithdrawn / abandoned Benton, INMISO Aug 2021target 2024
Kanoa Solar
Solar + storage
320 MWWithdrawn / abandoned Glenn, CACAISO Apr 2021target 2031
Callinan Solar And Storage
Solar + storage
320 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2031
Battery storage project 99, Pinal County
Battery storage
319 MWWithdrawn / abandoned Pinal, AZWest Sep 2021target 2025
Tamalpais Energy Storage
Battery storage
314 MWWithdrawn / abandoned Marin, CACAISO Apr 2021target 2030
Borealis Energy Storage
Battery storage
314 MWWithdrawn / abandoned Sonoma, CACAISO Apr 2021target 2030
Marnier
Solar + storage
309 MWWithdrawn / abandoned Merced, CACAISO Apr 2021target 2024
Japatul Valley Storage
Battery storage
308 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2024
Onshore wind project C1-49, Bonneville County
Onshore wind
308 MWWithdrawn / abandoned Bonneville, IDWest May 2021target 2024
Hog Island
Solar + storage
307 MWWithdrawn / abandoned Tulare, CACAISO Apr 2021target 2024
Copernicus
Solar + storage
306 MWWithdrawn / abandoned CACAISO Apr 2021target 2024
Epps Storage
Battery storage
305 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2021target 2026
Sciurus
Battery storage
304 MWWithdrawn / abandoned Orange, CACAISO Apr 2021target 2028
Paladin
Battery storage
304 MWWithdrawn / abandoned Orange, CACAISO Apr 2021target 2024
Amber Ray
Battery storage
304 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2027
BRP Parana BESS
Battery storage ยท BRP Parana BESS
304 MWWithdrawn / abandoned ERCOT May 2021target 2028
Amethyst Storage
Other ยท Riggs Energy Storage LLC
304 MWWithdrawn / abandoned Kaufman, TXERCOT Aug 2021target 2023
Finke River
Solar + storage
304 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2024
Balsam
Solar + storage
304 MWWithdrawn / abandoned Alameda, CACAISO Apr 2021target 2024
Stump Tail BESS
Other ยท Moccasin Pointe Grid, LLC
302 MWWithdrawn / abandoned Harris, TXERCOT Apr 2021target 2028
Battery storage project AG2-690, Sullivan County
Battery storage ยท Solar Prairie Holdco, LLC
300 MWWithdrawn / abandoned Sullivan, INPJM Mar 2021target 2024
Solar project J1886, Henderson County
Solar
300 MWWithdrawn / abandoned Henderson, KYMISO Aug 2021target 2025
Rocksdrift Energy Center
Solar ยท Rocksdrift Energy Center, LLC
300 MWWithdrawn / abandoned Herkimer, NYNYISO Jun 2021
Onshore wind project GEN-2021-058, Madison County
Onshore wind
300 MWWithdrawn / abandoned Madison, NESPP Apr 2021target 2026
Solar + storage project C1-47, Iron County
Solar + storage
300 MWWithdrawn / abandoned Iron, UTWest May 2021target 2025
Battery storage project LGE-GIS-2021-011, Jefferson County
Battery storage
300 MWWithdrawn / abandoned Jefferson, KYSoutheast Mar 2021target 2026
Solar project J2310, Beauregard Parish County
Solar
300 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2021target 2024
EI Steinway 2.1
Offshore wind ยท Beacon Wind LLC
300 MWWithdrawn / abandoned Queens, NYNYISO Jun 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)