๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Queue requests in study in the USA (2022 requests) โ€” page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,272255.2 GW
Active in queue299.4 GW1,514 requests
Agreement signed43.0 GW228 requests
Withdrawn1,886378.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,272 requests ยท page 5 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Company NS, Eureka County
Solar + storage
300 MWPaused / redesign Eureka, NVWest Sep 2022target 2029
Onshore wind project Company NA, White Pine County
Onshore wind
300 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Onshore wind project 118, Apache County
Onshore wind
300 MWIn study Apache, AZWest Apr 2022target 2025
Solar + storage project J3199, Adair County
Solar + storage
300 MWIn study Adair, MOMISO Sep 2022target 2026
Onshore wind project J2436, Webster County
Onshore wind
300 MWIn study Webster, IAMISO Sep 2022target 2030
Battery storage project GEN-2022-073, Clay County
Battery storage
300 MWIn study Clay, MOSPP Sep 2022target 2030
Solar + storage project 656, Jerome County
Solar + storage ยท Red Bridge Energy, LLC
300 MWPaused / redesign Jerome, IDWest May 2022target 2027
Solar + storage project Company MU, White Pine County
Solar + storage
300 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Solar + storage project Company ND, Lander County
Solar + storage
300 MWPaused / redesign Lander, NVWest Mar 2022target 2030
Wind + storage project IA-PNM-2023-08, Guadalupe County
Wind + storage
300 MWIn study Guadalupe, NMWest Dec 2022target 2025
Solar project J2446, Dunn County
Solar
300 MWIn study Dunn, WIMISO Sep 2022target 2027
Wind + storage project J3027, Stark County
Wind + storage
300 MWIn study Stark, ILMISO Sep 2022target 2027
Solar project 419, Big Horn County
Solar
300 MWIn study Big Horn, MTWest Feb 2022target 2025
Battery storage project AI1-018, Spotsylvania County
Battery storage
300 MWIn study Spotsylvania, VAPJM Apr 2022target 2026
Battery storage project J3216, Peoria County
Battery storage
300 MWIn study Peoria, ILMISO Sep 2022target 2027
Battery storage project J2423, Columbia County
Battery storage
300 MWIn study Columbia, WIMISO Sep 2022target 2027
Solar project J3045, Orange County
Solar
300 MWIn study Orange, TXMISO Sep 2022target 2026
Battery storage project Company 219, Clark County
Battery storage
300 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Solar + storage project GI-DISIS-2022-28, Kit Carson County
Solar + storage
299 MWPaused / redesign Kit Carson, COWest May 2022target 2029
Solar + storage project GI-DISIS-2022-45, Pueblo County
Solar + storage
299 MWPaused / redesign Pueblo, COWest May 2022target 2028
Solar + storage project GI-DISIS-2022-44, Moffat County
Solar + storage
299 MWPaused / redesign Moffat, COWest May 2022target 2030
Camino Ranch Storage SLF
Solar + storage ยท Camino Solar Ranch, LLC
298 MWIn study Houston, TXERCOT Oct 2022target 2028
Camino Ranch Solar SLF
Solar + storage ยท Camino Ranch Solar Project LLC
296 MWIn study Houston, TXERCOT Oct 2022target 2028
Solar project J1743, Miami County
Solar
293 MWIn study Miami, INMISO Apr 2022target 2026
Solar project AI1-085, Wayne County
Solar
290 MWIn study Wayne, INPJM Jul 2022target 2030
Solar project AH2-322, Pittsylvania County
Solar
290 MWIn study Pittsylvania, VAPJM Mar 2022target 2025
Onshore wind project G0761, Grant County
Onshore wind
290 MWIn study Grant, WAWest Jun 2022target 2026
Solar project GEN-2022-016, Woodward County
Solar
288 MWIn study Woodward, OKSPP Jun 2022target 2028
Solar + storage project J3002, Pine County
Solar + storage
288 MWIn study Pine, MNMISO Sep 2022target 2025
Solar project J3012, Coles County
Solar
287 MWIn study Coles, ILMISO Sep 2022target 2026
Battery storage project AI1-187, Hunterdon County
Battery storage
280 MWIn study Hunterdon, NJPJM Sep 2022target 2027
Solar project J3014, Rapides Parish County
Solar
280 MWIn study Rapides Parish, LAMISO Sep 2022target 2026
Solar project AH2-342, Stark County
Solar
280 MWIn study Stark, ILPJM Mar 2022target 2027
Battery storage project G0724, Curry County
Battery storage
280 MWIn study Curry, ORWest Jan 2022target 2026
Solar + storage project 26, Sacramento County
Solar + storage
275 MWIn study Sacramento, CAWest Sep 2022target 2030
Solar + storage project 119, Greenlee County
Solar + storage
270 MWIn study Greenlee, AZWest Apr 2022target 2027
Solar + storage project GI-2022-162, Imperial County
Solar + storage
270 MWIn study Imperial, CAWest Sep 2022target 2026
Solar project GEN-2022-015, Decatur County
Solar
270 MWIn study Decatur, KSSPP Jun 2022target 2028
Solar project J2565, Iroquois County
Solar
265 MWIn study Iroquois, ILMISO Sep 2022target 2026
Gas project J3047, Adair County
Gas
263 MWIn study Adair, IAMISO Sep 2022target 2027
Gas project J2791, Lafayette Parish County
Gas
263 MWIn study Lafayette Parish, LAMISO Sep 2022target 2027
Masava Storage
Battery storage ยท Savannah Oaks Solar Project, LLC
257 MWIn study Madison, TXERCOT Sep 2022target 2028
Bayside 2 BESS
Battery storage
252 MWPaused / redesign Dewitt, TXERCOT Mar 2022
Onshore wind project J3078, Peoria County
Onshore wind
252 MWIn study Peoria, ILMISO Sep 2022target 2026
Solar + storage project Q475, Maricopa County
Solar + storage
250 MWIn study Maricopa, AZWest Mar 2022target 2025
Solar project AI1-040, Elk County
Solar
250 MWIn study Elk, PAPJM Apr 2022target 2025
Battery storage project J2628, Huron County
Battery storage
250 MWIn study Huron, MIMISO Sep 2022target 2028
Solar + storage project AH2-112, St. Joseph County
Solar + storage
250 MWIn study St. Joseph, INPJM Feb 2022target 2026
Battery storage project AI1-149, Mchenry County
Battery storage
250 MWIn study Mchenry, ILPJM Sep 2022target 2025
Solar project J2793, Saline County
Solar
250 MWIn study Saline, ILMISO Sep 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)