United States › Grid › Interconnection queues › Colorado
SOLAR + STORAGE · WESTSolar + storage project GI-DISIS-2022-44, Moffat County
Solar + storage project GI-DISIS-2022-44, Moffat County is a 299 MW solar + storage request suspended in the West interconnection queue, in Moffat County, Colorado, connecting to Tri-State Generation and Transmission Association.
- PlanningQueued May 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GI-DISIS-2022-44
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Tri-State Generation and Transmission Association
- Connection point (POI)
- Craig 345kV Substation
- Location
- Moffat County, Colorado
- Technology
- Solar: 199 MW · Battery: 100 MW
- Total requested
- 299 MW
- Service type
- Network resource (NRIS)
- Study phase
- Suspended LGIA
- Queue status
- Suspended
- Entered queue
- 31 May 2022
- Proposed online date
- June 2030
Location
Marker shows the centre of Moffat County; the queue data does not give exact sites.
Other requests in Moffat County
- Solar project GI-TC-2021-01, Moffat CountySolar · 145 MW · agreement signed
- Battery storage project GI-RSC-2025-02, Moffat CountyBattery storage · 200 MW · in study
- Solar + storage project GI-CS-2025-17, Moffat CountySolar + storage · 200 MW · in study
- Solar + storage project 1118, Moffat CountySolar + storage · 350 MW · withdrawn
- Gas project GI-RSC-2025-01, Moffat CountyGas · 307 MW · withdrawn
- Solar + storage project C2-163, Moffat CountySolar + storage · 220 MW · withdrawn
- Solar + storage project GI-TC-2024-33, Moffat CountySolar + storage · 199 MW · withdrawn
- Solar project GI-TC-2024-32, Moffat CountySolar · 66.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem