GAS · MISOGas project J3047, Adair County
Gas project J3047, Adair County is a 263 MW gas request in interconnection study in the MISO interconnection queue, in Adair County, Iowa, connecting to MIDAMERICAN ENERGY CO..
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3047
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MIDAMERICAN ENERGY CO.
- Connection point (POI)
- ORIENT - NORTHBORO 345.0kV
- Location
- Adair County, Iowa
- Technology
- Gas: 263 MW
- Total requested
- 263 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- September 2027
Location
Marker shows the centre of Adair County; the queue data does not give exact sites.
Other requests in Adair County
- Orient Energy CenterGas · 265 MW · in study
- Surplus; J500Gas · 263 MW · in study
- Onshore wind project J500, Adair CountyOnshore wind · 500 MW · built
- Onshore wind project J499, Adair CountyOnshore wind · 340 MW · built
- Onshore wind project J527, Adair CountyOnshore wind · 250 MW · built
- Onshore wind project R38, Adair CountyOnshore wind · 200 MW · built
- Onshore wind project R41, Adair CountyOnshore wind · 100 MW · built
- Gas project J355, Adair CountyGas · 810 MW · withdrawn
- Onshore wind project R52, Adair CountyOnshore wind · 500 MW · withdrawn
- Gas project J364, Adair CountyGas · 464 MW · withdrawn
- Gas project J3553, Adair CountyGas · 263 MW · withdrawn
- Onshore wind project J528, Adair CountyOnshore wind · 200 MW · withdrawn